City of Redmond, OR
Reviewed intelligence covers 1 project across procurement. Current commercial scope concentrates on process and controls and pumping and storage.
Last verified Oct 13, 2026 1 published project history
- Last verified
- Oct 13, 2026
- Reviewed portfolio
- 1 project
- Source families
- 1 official family
- Historical depth
- 2026
Account brief
Current reviewed account position
Current Waterline IQ coverage includes 1 published project history across active solicitation. Accepted project records cover water infrastructure with sector detail still incomplete, with reviewed work concentrated in process and controls and pumping and storage. This is a portfolio-derived account view, not a complete capital-program, staffing, facility, or procurement inventory.
- Published projects
- 1
- Official source families
- 1
- Lifecycle breadth
- 1 stage
- Recent material changes
- 1
- Nearest external milestone
- Timing not yet reviewed
What changed
Highest-value recent account changes
-
Procurement
Formal procurement opportunity published
The formal pursuit window is active or has materially changed.
Yew Lift Station Improvement Project · Sep 17, 2026
Reviewed project portfolio
What the owner is planning and building
Active solicitation
1Upcoming external milestones
Next reviewed decision points
Official response deadline
Yew Lift Station Improvement Project
- Timing
- Timing not yet reviewed
- Confidence
- Timing unknown
- Could change timing
- Funding status is not established in reviewed records.
Funding profile
Funding progression by project
No accepted funding record or reviewed funding signal is available.
Procurement and delivery
Reviewed buying position
Yew Lift Station Improvement Project
Active solicitation
Active solicitation
Organizations and relationships
Documented project-specific roles
No consultant, contractor, funding-agency, or partner relationship has been accepted for this portfolio.
Facilities and systems
Commercially relevant public assets
No reviewed facility record is available. Waterline IQ does not infer facilities from project names.
Consequential unknowns and conflicts
What current coverage does not establish
-
Coverage boundary
Portfolio completeness is not established
Current coverage includes published Waterline IQ project histories; it is not a complete capital-program inventory.
-
Coverage limitation
Yew Lift Station Improvement Project
Initial project record from an official solicitation; earlier planning history is not yet established.
Open project
Chronological owner activity
Complete reviewed account history
-
Procurement · Project-level
Formal procurement opportunity published
Yew Lift Station Improvement Project: The Yew Avenue Wastewater Lift Station Improvements Project consists of constructing upgrades to the City’s existing wastewater lift station to improve electrical reliability, provide standalone backup power, and support future operational and capacity needs. Work includes installing a new outdoor-rated control cabinet with updated pump controls and instrumentation, adding a new generator system with automatic transfer capability, and expanding the lift station site to accommodate the upgraded electrical equipment and improved access. Additional work includes minor mechanical and electrical improvements and complete site restoration. All improvements shall comply with current Oregon Department of Environmental Quality (DEQ) wastewater pump station design standards and applicable electrical and safety codes. The City estimates the cost of improvements at $450,000. All workmanship, materials, and conditions shall conform to applicable construction codes, specifications included on plans, any special provisions included in these documents, issued addendums, the General Conditions, Special Provisions, Redmond Standards & Specifications 2024 and any Supplementary Conditions. Responses due 2026-10-20.
Yew Lift Station Improvement Project · Official evidence
Source coverage and freshness
What Waterline IQ has reviewed
BidLocker Oregon agency procurement discovery
Oregon public agencies via BidLocker
Evidence and official sources
Accepted owner and portfolio facts
Evidence and material facts — 1 verified claims
Project scope
The Yew Avenue Wastewater Lift Station Improvements Project consists of constructing upgrades to the City’s existing wastewater lift station to improve electrical reliability, provide standalone backup power, and support future operational and capacity needs. Work includes installing a new outdoor-rated control cabinet with updated pump controls and instrumentation, adding a new generator system with automatic transfer capability, and expanding the lift station site to accommodate the upgraded electrical equipment and improved access. Additional work includes minor mechanical and electrical improvements and complete site restoration. All improvements shall comply with current Oregon Department of Environmental Quality (DEQ) wastewater pump station design standards and applicable electrical and safety codes. The City estimates the cost of improvements at $450,000. All workmanship, materials, and conditions shall conform to applicable construction codes, specifications included on plans, any special provisions included in these documents, issued addendums, the General Conditions, Special Provisions, Redmond Standards & Specifications 2024 and any Supplementary Conditions.
“The Yew Avenue Wastewater Lift Station Improvements Project consists of constructing upgrades to the City’s existing wastewater lift station to improve electrical reliability, provide standalone backup power, and support future operational and capacity needs. Work includes installing a new outdoor-rated control cabinet with updated pump controls and instrumentation, adding a new generator system with automatic transfer capability, and expanding the lift station site to accommodate the upgraded electrical equipment and improved access. Additional work includes minor mechanical and electrical improvements and complete site restoration. All improvements shall comply with current Oregon Department of Environmental Quality (DEQ) wastewater pump station design standards and applicable electrical and safety codes. The City estimates the cost of improvements at $450,000. All workmanship, materials, and conditions shall conform to applicable construction codes, specifications included on plans, any special provisions included in these documents, issued addendums, the General Conditions, Special Provisions, Redmond Standards & Specifications 2024 and any Supplementary Conditions.”