Huntington Well, Pump Station, Storage, and Transmission Improvements
The project entails: drilling a new well, adding a pump station, adding a back up generator, adding a new storage tank and transmission line on the east side of town.
Last verified Jul 14, 2026 2 official source families
Project brief
What is proposed
The project entails: drilling a new well, adding a pump station, adding a back up generator, adding a new storage tank and transmission line on the east side of town.
Latest material change
Added during OHA's 3Q2026 DWSRF priority-list cycle
OHA lists the project for DWSRF funding consideration; the workbook does not establish a formal procurement date.
Commercial scope
Confirmed work and commercial interpretation
What is proposed
The project entails: drilling a new well, adding a pump station, adding a back up generator, adding a new storage tank and transmission line on the east side of town.
Potential commercial work
Waterline IQ interpretation of accepted scope. These items are not confirmed contract packages or specifications.
Pumping and storage
Water well drilling and Water storage tank
Distribution
Water main replacement, Water main fittings, and Valves and appurtenances
Process and controls
Electrical and controls
Civil and site work
Trenching and restoration
Selected lifecycle
Key official milestones
-
Official event
OHA surveys Huntington's active drinking-water system
OHA's inventory records the most recent system survey date; this is contextual system evidence, not a project announcement.
View evidence for OHA surveys Huntington's active drinking-water system -
Official event
Added during OHA's 3Q2026 DWSRF priority-list cycle
OHA lists the project for DWSRF funding consideration; the workbook does not establish a formal procurement date.
View evidence for Added during OHA's 3Q2026 DWSRF priority-list cycle
Evidence and sources
11 accepted claims across 2 official document versions
Selected official evidence · Inspect exact excerpts and locators
2026 Q3 Combined Base DWSRF and IIJA General Supplemental PPL
OHA DWSRF infrastructure project priority list“11 | City of Huntington SD-26-20 Baker Brian McDowell / Gail Nelson 510 | | Issue: The water system has one well and experience areas of town where the 20psi is not maintained at all times. This is documented in the draft WSMP. Project: The project entails...”
Huntington, City of — OHA inventory OR41-00393
OHA drinking-water system inventory — Huntington“ | Distribution class: 1 | Last Survey Date: Jun 02, 2023”