Weston Well, Storage, Pump Station, and Distribution Improvements
The project entails: drilling a new well, adding a pump station, adding a back up generator, adding a new storage tank, transmission line upsize and other distribution items(current reservoir maintenance, new water meters and new fire hydrants).
Last verified Sep 25, 2026 3 official source families
Project brief
What is proposed
The project entails: drilling a new well, adding a pump station, adding a back up generator, adding a new storage tank, transmission line upsize and other distribution items(current reservoir maintenance, new water meters and new fire hydrants).
Latest material change
Added during OHA's 3Q2026 DWSRF priority-list cycle
OHA lists the project for DWSRF funding consideration; the workbook does not establish a formal procurement date.
Commercial scope
Confirmed work and commercial interpretation
What is proposed
The project entails: drilling a new well, adding a pump station, adding a back up generator, adding a new storage tank, transmission line upsize and other distribution items(current reservoir maintenance, new water meters and new fire hydrants).
Potential commercial work
Waterline IQ interpretation of accepted scope. These items are not confirmed contract packages or specifications.
Distribution
Water meters and Fire hydrants
Pumping and storage
Water well drilling and Water storage tank
Process and controls
Electrical and controls
Civil and site work
Trenching and restoration
Selected lifecycle
Key official milestones
-
Official event
Council considers engineering and USDA planning support
Council minutes document engineering-services and possible USDA SEARCH grant work for the water system master plan.
View evidence for Council considers engineering and USDA planning support -
Official event
Added during OHA's 3Q2026 DWSRF priority-list cycle
OHA lists the project for DWSRF funding consideration; the workbook does not establish a formal procurement date.
View evidence for Added during OHA's 3Q2026 DWSRF priority-list cycle
Evidence and sources
10 accepted claims across 3 official document versions
Selected official evidence · Inspect exact excerpts and locators
City of Weston Bids and RFPs
Weston official bids and RFPs“There are no bids or RFPs available.”
2026 Q3 Combined Base DWSRF and IIJA General Supplemental PPL
OHA DWSRF infrastructure project priority list“11 | City of Weston SD-26-12 Umatilla Ryan DeGrofft / Gail Nelson 714 | | Issue: The water system has one well and experience areas of town where the 20psi is not maintained at all times. This is documented in the draft WSMP. Project: The project entails: ...”
Weston City Council minutes — February 14, 2024
Weston City Council water-system planning minutes“Brad Baird from Anderson Perry presented information in addition to an updated engineering services contract for possible USDA Search Grant for the water system master plan. An agreement for professional series for the development code codification and refo...”