ITB - Foothill Drive Sanitary Sewer Upgrade Project No. 7207
The Project consists of the following work: This Project consists of upsizing an existing 1,587 linear feet, 10-inch sanitary sewer line to a 14-inch sanitary sewer line through the pipebursting method within Commonwealth Lake Park.
Last verified Oct 9, 2026 2 official source families
Project brief
What is proposed
The Project consists of the following work: This Project consists of upsizing an existing 1,587 linear feet, 10-inch sanitary sewer line to a 14-inch sanitary sewer line through the pipebursting method within Commonwealth Lake Park.
Latest material change
FY2026–27 adopted budget lists $910,000 for Foothill project 7207
The adopted budget lists $910,000 FY27 for project 7207 in Fund 112, Sanitary Sewer Construction Fund. This is an owner budget allocation, not an external funding award or contractor amount. July 1 represents the fiscal-year boundary; the exact adoption/publication date is not established here.
Commercial scope
Confirmed work and commercial interpretation
What is proposed
The Project consists of the following work: This Project consists of upsizing an existing 1,587 linear feet, 10-inch sanitary sewer line to a 14-inch sanitary sewer line through the pipebursting method within Commonwealth Lake Park.
Potential commercial work
Waterline IQ interpretation of accepted scope. These items are not confirmed contract packages or specifications.
Wastewater collection
Gravity sewer main and Sewer piping
Permits and approvals
Documented permitting
Permit records have not been captured; requirements and approval remain unverified.
Selected lifecycle
Key official milestones
-
Official event
FY23 planning began for Commonwealth Lake sewer capacity upgrade
The proposed FY2027–2031 CIP retrospectively reports planning began in FY23 (FY2022–23). The stored July 1 date represents the fiscal-year boundary, not an actual action/publication date. Planning scope was 1,587 LF from 10-inch to 12-inch within Commonwealth Lake Park; the later formal procurement specifies 14-inch.
View evidence for FY23 planning began for Commonwealth Lake sewer capacity upgrade -
Official event
Official solicitation scope changed
ITB - Foothill Drive Sanitary Sewer Upgrade Project No. 7207: The official record establishes a formal response path. Responses due 2026-07-14.
View evidence for Official solicitation scope changed -
Official event
FY2026–27 adopted budget lists $910,000 for Foothill project 7207
The adopted budget lists $910,000 FY27 for project 7207 in Fund 112, Sanitary Sewer Construction Fund. This is an owner budget allocation, not an external funding award or contractor amount. July 1 represents the fiscal-year boundary; the exact adoption/publication date is not established here.
View evidence for FY2026–27 adopted budget lists $910,000 for Foothill project 7207
Evidence and sources
3 accepted claims across 4 official document versions
Selected official evidence · Inspect exact excerpts and locators
Fiscal Year 2026-27: FY 2026-27 Adopted Budget
Clean Water Services budgets and capital planning publications“FOOTHILL DR (COMMONWEALTH LAKE) SANITARY UPGRADE 7207 112 750,000 130,000 910,000 - - - - 910,000”
Fiscal Year 2026-27: FY 2027-2031 Capital Improvement Plan
Clean Water Services budgets and capital planning publications“Project Detail Project Name: FOOTHILL DR (COMMONWEALTH LAKE) SANITARY UPGRADE Project Number: 7207 Project Subtype: Sanitary Collection System Fund: 112 - Sanitary Sewer Construction Fund Project Manager: Doug Gresham Project Status: Open Department/Program...”
ITB - Foothill Drive Sanitary Sewer Upgrade Project No. 7207 — 6119
Clean Water Services formal opportunities“ITB - Foothill Drive Sanitary Sewer Upgrade Project No. 7207”