Owner type
Governance type not yet classified
Geography
Reviewed projects · Portland, Oregon
Reviewed sectors
Wastewater

City of Portland

Reviewed intelligence covers 1 project across design. Current commercial scope concentrates on civil and site work, process and controls, and pumping and storage.

Last verified Oct 9, 2026 1 published project history

Last verified
Oct 9, 2026
Reviewed portfolio
1 project
Source families
2 official families
Historical depth
Unknown

What changed

Highest-value recent account changes

0 published material signals

No separate reviewed material account change has been published.

Reviewed project portfolio

What the owner is planning and building

Published coverage, not a complete capital program

Design / permitting

1
Project

Force Avenue Pump Station Upgrade

Portland, Oregon

Current position Design Unknown · Not yet researched
Latest change FY2026–27 adopted capital book lists Force Avenue project E10611 FY 2026
Confirmed scope Process and controls, Pumping and storage, Wastewater collection, and Civil and site work
Next external milestone Verify design completion, current construction advertisement and the anticipated December 2026 start Timing not yet reviewed · Timing unknown
Evidence / exception 2 official source families Last verified Oct 9, 2026

Upcoming external milestones

Next reviewed decision points

Chronological, bounded forecasts
Permit or design gate

Verify design completion, current construction advertisement and the anticipated December 2026 start

Force Avenue Pump Station Upgrade

Timing
Timing not yet reviewed
Confidence
Timing unknown
Could change timing
Funding status is not established in reviewed records.
The project page publishes an anticipated December 2026 start alongside older design-through-2025 language. These originals do not establish the current procurement, issued permits or an executed contract, so a reliable normalized procurement window is not assigned.

Funding profile

Funding progression by project

No accepted funding record or reviewed funding signal is available.

Procurement and delivery

Reviewed buying position

Organizations and relationships

Documented project-specific roles

Not account-wide incumbency

No consultant, contractor, funding-agency, or partner relationship has been accepted for this portfolio.

Facilities and systems

Commercially relevant public assets

Public information only

No reviewed facility record is available. Waterline IQ does not infer facilities from project names.

Consequential unknowns and conflicts

What current coverage does not establish

Ranked qualification limits
  1. Coverage boundary

    Portfolio completeness is not established

    Current coverage includes published Waterline IQ project histories; it is not a complete capital-program inventory.

  2. Procurement research

    Force Avenue Pump Station Upgrade: procurement has not yet been researched

    No conclusion about solicitation timing, delivery method, or procurement status should be drawn from current coverage.

    Open project
  3. Coverage limitation

    Force Avenue Pump Station Upgrade

    Earliest publication and first public Signal dates are unknown; retrieval/review dates do not establish them.

    Open project

Chronological owner activity

Complete reviewed account history

Official event date · newest first
  1. Baseline history · Project-level

    FY2026–27 adopted capital book lists Force Avenue project E10611

    The adopted capital chapter lists $350,000 FY2026–27 expenditure and $5,370,000 across five fiscal years. This is a fiscal-year capital plan; it does not establish when design, procurement, financing or construction occurred. Supplemental budget amendments were not reviewed and may change allocations.

    Force Avenue Pump Station Upgrade · Official evidence
  2. Baseline history · Project-level

    First Force Avenue air-release-valve component completed

    The official project page reports the Columbia Slough Trail ARV completed in October 2022. This is one component only; it does not establish completion of the main pump-station upgrade or the second planned ARV.

    Force Avenue Pump Station Upgrade · Official evidence

Source coverage and freshness

What Waterline IQ has reviewed

Historical depthUnknown
Official document versions2
Last successful reviewOct 9, 2026
Accepted claims5

Portland BES planning, design and construction publication discovery

Portland Bureau of Environmental Services

OperatingLast validated traversal Oct 8, 2026

Portland Water and BES published adopted capital-budget chapters

City of Portland

OperatingLast validated traversal Oct 9, 2026

Evidence and official sources

Accepted owner and portfolio facts

5 accepted claims
Evidence and material facts — 5 verified claims
Portfolio-derived · Force Avenue Pump Station Upgrade

Published funding description

The capital book describes bond proceeds repaid by sanitary sewer and stormwater rates. No financing agreement, bond issuance date, funding award or construction contract was verified.

“Funded by bond proceeds repaid by sanitary sewer and stormwater rates.”
/publishedMarkup :: div#story-viewer-layout:nth-of-type(1) > div#b6b04411-b14d-4e35-802c-dfae3390e3ec:nth-of-type(3) > div:nth-of-type(1) > div#37e4f3f8-8bf0-41e4-9c4f-d58ea70e0b5f:nth-of-type(2) > div:nth-of-type(1) > div#03efd6bd-8ecb-4c69-9036-75d7b0eab291:nth-of-type(7) > div:nth-of-type(2) > div:nth-of-type(1) > p:nth-of-type(1)Published UnknownOpen exact evidenceOfficial source
Portfolio-derived · Force Avenue Pump Station Upgrade

Project scope

Project originated in the Pump Station Improvement Program. Remodel pump station for improved reliability and maintenance. Remodel includes wet well modification, new submersible pumps, onsite electrical controls building and generator shelter, and odor treatment.

“Project originated in the Pump Station Improvement Program. Remodel pump station for improved reliability and maintenance. Remodel includes wet well modification, new submersible pumps, onsite electrical controls building and generator shelter, and odor treatment.”
/publishedMarkup :: div#story-viewer-layout:nth-of-type(1) > div#b6b04411-b14d-4e35-802c-dfae3390e3ec:nth-of-type(3) > div:nth-of-type(1) > div#37e4f3f8-8bf0-41e4-9c4f-d58ea70e0b5f:nth-of-type(2) > div:nth-of-type(1) > div#bc5d9703-ef6e-4063-bc52-e2cadb3b8986:nth-of-type(5) > div:nth-of-type(2) > div:nth-of-type(1) > p:nth-of-type(1)Published UnknownOpen exact evidenceOfficial source
Portfolio-derived · Force Avenue Pump Station Upgrade

Planned capital expenditure

FY2026–27 adopted capital book: $350,000 FY2026–27 expenditure; $5,370,000 five-year expenditure total through FY2030–31. The prior-year and FY2025–26 revised columns are separate. Planning/budget amounts are not a construction contract, executed financing or the projected total project cost.

“Total Expenditures | $1,767,548 | $350,000 | $350,000 | $0 | $2,100,000 | $2,800,000 | $120,000 | $5,370,000”
/publishedMarkup :: div#story-viewer-layout:nth-of-type(1) > div#b6b04411-b14d-4e35-802c-dfae3390e3ec:nth-of-type(3) > div:nth-of-type(1) > div#37e4f3f8-8bf0-41e4-9c4f-d58ea70e0b5f:nth-of-type(2) > div:nth-of-type(1) > div#5d4ba429-3bcd-464c-ab4b-1af7e23f5c00:nth-of-type(3) > div:nth-of-type(2) > div:nth-of-type(1) > table:nth-of-type(1) > tbody:nth-of-type(1) > tr:nth-of-type(1)Published UnknownOpen exact evidenceOfficial source
Portfolio-derived · Force Avenue Pump Station Upgrade

Official project identifier

Portland BES capital project E10611

“E10611 - Force Ave. Pump Station Upgrade”
/publishedMarkup :: div#story-viewer-layout:nth-of-type(1) > div#3d51965a-378a-4393-9410-8ee30d036075:nth-of-type(2) > div:nth-of-type(1) > div#454f208a-2736-4dd1-b96e-0d173e036ff3:nth-of-type(2) > div:nth-of-type(1) > div#6d177bde-66de-4a61-b30b-2af55229111d:nth-of-type(2) > div:nth-of-type(2) > div:nth-of-type(1) > h1:nth-of-type(1)Published UnknownOpen exact evidenceOfficial source
Portfolio-derived · Force Avenue Pump Station Upgrade

Published schedule and uncertainty

Official page anticipates construction starting December 2026 for two years and says contractor advertisement/bid/selection will follow design. Its older 'Design will continue through 2025' text remains. Current design completion, open procurement and awarded contract status need verification.

“Design will continue through 2025. The contractor advertisement, bid, and selection process will follow. Construction is anticipated to begin in December of 2026 and take two years to complete.”
body:nth-of-type(1) > div:nth-of-type(1) > main#main-content:nth-of-type(1) > div:nth-of-type(1) > div:nth-of-type(1) > div:nth-of-type(1) > div:nth-of-type(1) > div#block-cloudy-content:nth-of-type(2) > div:nth-of-type(1) > div:nth-of-type(1) > div:nth-of-type(1) > article:nth-of-type(1) > div:nth-of-type(5) > div:nth-of-type(1) > p:nth-of-type(3)Published UnknownOpen exact evidenceOfficial source