Location
Portland, Oregon

Force Avenue Pump Station Upgrade

Project originated in the Pump Station Improvement Program. Remodel pump station for improved reliability and maintenance. Remodel includes wet well modification, new submersible pumps, onsite electrical controls building and generator shelter, and odor treatment.

Last verified Oct 9, 2026 2 official source families

What is proposed

Project originated in the Pump Station Improvement Program. Remodel pump station for improved reliability and maintenance. Remodel includes wet well modification, new submersible pumps, onsite electrical controls building and generator shelter, and odor treatment.

FY2026–27 adopted capital book lists Force Avenue project E10611

The adopted capital chapter lists $350,000 FY2026–27 expenditure and $5,370,000 across five fiscal years. This is a fiscal-year capital plan; it does not establish when design, procurement, financing or construction occurred. Supplemental budget amendments were not reviewed and may change allocations.

Verify design completion, current construction advertisement and the anticipated December 2026 start

Timing is not established in reviewed records.

Confirmed work and commercial interpretation

What is proposed

Project originated in the Pump Station Improvement Program. Remodel pump station for improved reliability and maintenance. Remodel includes wet well modification, new submersible pumps, onsite electrical controls building and generator shelter, and odor treatment.

Potential commercial work

Waterline IQ interpretation of accepted scope. These items are not confirmed contract packages or specifications.

Process and controls

Electrical and controls

Pumping and storage

Sewage pumps and Emergency generators

Wastewater collection

Force main appurtenances

Civil and site work

Concrete and structural

Documented permitting

Permit records have not been captured; requirements and approval remain unverified.

Key official milestones

  1. Official event

    First Force Avenue air-release-valve component completed

    The official project page reports the Columbia Slough Trail ARV completed in October 2022. This is one component only; it does not establish completion of the main pump-station upgrade or the second planned ARV.

    View evidence for First Force Avenue air-release-valve component completed
  2. Official event

    FY2026–27 adopted capital book lists Force Avenue project E10611

    The adopted capital chapter lists $350,000 FY2026–27 expenditure and $5,370,000 across five fiscal years. This is a fiscal-year capital plan; it does not establish when design, procurement, financing or construction occurred. Supplemental budget amendments were not reviewed and may change allocations.

    View evidence for FY2026–27 adopted capital book lists Force Avenue project E10611
Evidence and sources
5 accepted claims across 2 official document versions
Selected official evidence · Inspect exact excerpts and locators

Force Avenue Pump Station Project

Portland BES planning, design and construction publication discovery
Inspect exact excerpt and locator
“Design will continue through 2025. The contractor advertisement, bid, and selection process will follow. Construction is anticipated to begin in December of 2026 and take two years to complete.”

Force Avenue Pump Station Project

Portland BES planning, design and construction publication discovery
Inspect exact excerpt and locator
“The first ARV is located along the Columbia Slough Trail at a point east of Moore Island and across from an access road off N Cottonwood Street. Construction was completed in October of 2022.”

Fiscal Year 2026-27 Adopted Budget — E10611 - Force Ave. Pump Station Upgrade

Portland Water and BES published adopted capital-budget chapters
Inspect exact excerpt and locator
“Total Expenditures | $1,767,548 | $350,000 | $350,000 | $0 | $2,100,000 | $2,800,000 | $120,000 | $5,370,000”