Reviewed projects · Stayton, Oregon
Reviewed sectors
Drinking water

City of Stayton

Reviewed intelligence covers 1 project across funding pipeline. Current commercial scope concentrates on pumping and storage and treatment plant.

Last verified Sep 25, 2026 1 published project history

Last verified
Sep 25, 2026
Reviewed portfolio
1 project
Source families
3 official families
Historical depth
2026

What changed

Highest-value recent account changes

1 published material signal

Reviewed project portfolio

What the owner is planning and building

Published coverage, not a complete capital program

Funding pipeline

1
Project

Stayton Water Treatment Resilience Improvements

Stayton, Oregon · SD-26-24

Current position Funding pipeline Requested / Priority-listed · Active solicitation
Latest change Added during OHA's 3Q2026 DWSRF priority-list cycle Q3 2026
Confirmed scope Treatment plant and Pumping and storage
Next external milestone Complete the progressive design-build selection and execute the ASR contract Jul 2026–Oct 2026 · High confidence
Evidence / exception 3 official source families Last verified Sep 25, 2026

Upcoming external milestones

Next reviewed decision points

Chronological, bounded forecasts
Active procurement

Complete the progressive design-build selection and execute the ASR contract

Stayton Water Treatment Resilience Improvements

Timing
Jul 2026–Oct 2026
Confidence
High confidence
Could change timing
Requested / Priority-listed funding is documented; no award or executed financing is established.
RFQ Water/26/01 publishes proposal, selection, council-approval, execution, and notice-to-proceed milestones through October 2026.

Funding profile

Funding progression by project

Procurement and delivery

Reviewed buying position

Organizations and relationships

Documented project-specific roles

Not account-wide incumbency

No consultant, contractor, funding-agency, or partner relationship has been accepted for this portfolio.

Facilities and systems

Commercially relevant public assets

Public information only

No reviewed facility record is available. Waterline IQ does not infer facilities from project names.

Consequential unknowns and conflicts

What current coverage does not establish

Ranked qualification limits
  1. Coverage boundary

    Portfolio completeness is not established

    Current coverage includes published Waterline IQ project histories; it is not a complete capital-program inventory.

  2. Funding position

    Stayton Water Treatment Resilience Improvements: no award or executed financing is established

    No award confirmed

    Open project
  3. Coverage limitation

    Stayton Water Treatment Resilience Improvements

    The reviewed RFQ establishes the planned selection schedule; subsequent shortlist, RFP, award, and notice-to-proceed actions require verification.

    Open project

Chronological owner activity

Complete reviewed account history

Official event date · newest first
  1. Funding signal · Project-level

    Added during OHA's 3Q2026 DWSRF priority-list cycle

    OHA lists the project for DWSRF funding consideration; the workbook does not establish a formal procurement date.

    Stayton Water Treatment Resilience Improvements · Official evidence
  2. Baseline history · Project-level

    Aquifer storage and recovery RFQ issued

    The City issued the first step of a two-step progressive design-build procurement for the ASR project.

    Stayton Water Treatment Resilience Improvements · Official evidence

Source coverage and freshness

What Waterline IQ has reviewed

Historical depth2026
Official document versions3
Last successful reviewSep 25, 2026
Accepted claims11

OHA DWSRF infrastructure project priority list

Oregon Health Authority

HealthyLast success Sep 25, 2026

OHA DWSRF infrastructure project priority list — public-comment edition

Oregon Health Authority

HealthyLast success Sep 25, 2026

Stayton aquifer-storage-and-recovery project updates

City of Stayton

HealthyLast success Sep 25, 2026

Evidence and official sources

Accepted owner and portfolio facts

11 accepted claims
Evidence and material facts — 11 verified claims
Owner fact · City of Stayton

Organization governance type

city_municipality

“City of Stayton”
Portfolio-derived · Stayton Water Treatment Resilience Improvements

Active procurement

Progressive design-build RFQ Water/26/01 for the aquifer storage and recovery project

“Activity/Event Anticipated Date Invitation to receive RFQ March 13,2026 RFQ Issued April 07, 2026 SOQ Due May04,2026 Shortlist Approved May25,2026 Notice ofIntent to Issue RFP May26,2026 RFPIssued June 04, 2026 ProposalsDue July28,2026 Selection Complete August25,2026 Notice ofintent to award September16, 2026 Council Approval October05, 2026 Contract Executed October20, 2026 Notice to Proceed (NTP) October28, 2026 3 PROJECTOVERVIEW The Cityof Stayton (“City”) islocatedin Marion County, Oregon. The City’s primarypotable water supplyis derivedfromthe North SantiamRiver. This source is periodicallysubjecttoharmful algal blooms, high turbidityduring wintermonths, upstreamcontamination risk, andreducedsummer flows thatlimitavailable waterrights during peak demandperiods. Toimprove systemreliabilityandresilience, the Cityhas undertaken planning andfeasibility efforts todevelopan AquiferStorage andRecovery(ASR) system. A feasibilitystudyand test well drillingprogram completed in 2022confirmed thetechnical viabilityofimplementingan ASR system at theCity-owned MillCreek Park site. Also,a SeasonallyVaryingFlows determination technical studyhas been performedandcompletedby the Oregon Water Resources Department(OWRD). The ASRsystemis intendedtoallowtreatedpotable watertobe injectedintoa deepaquiferduring periods of excess supplyandrecoveredduring high-demandor emergencyconditions. The Cityhas securedgrantfunding fromthe OWRD andhas dedicatedSystemDevelopment Charge (SDC) funds tosupportthe design andconstruction of the ASRsystem. 4 ANTICIPATED SCOPEOFSERVICES The anticipatedscope of work mayinclude, butis notlimitedto: • ASR production andinjection well(s) • Well pumpandmechanical systems • Injection andrecoverypiping • Evaluate waterdistribution systems • QuantifyandConfirm ASR utilization potential Aquifer StorageandRecoveryProject(RFQ) Page 8 of21”
Portfolio-derived · Stayton Water Treatment Resilience Improvements

Oha dwsrf loi

SD-26-24

“SD-26-24”
Portfolio-derived · Stayton Water Treatment Resilience Improvements

Priority rank

22

“22”
Portfolio-derived · Stayton Water Treatment Resilience Improvements

Project focus

Source

“Source”
Portfolio-derived · Stayton Water Treatment Resilience Improvements

Amount requested

$2,871,000 USD

“2871000”
Portfolio-derived · Stayton Water Treatment Resilience Improvements

Disadvantaged community

Yes

“Yes”
Portfolio-derived · Stayton Water Treatment Resilience Improvements

Ppl quarter added

3Q2026

“3Q2026”
Portfolio-derived · Stayton Water Treatment Resilience Improvements

Project rating

31

“31”
Portfolio-derived · Stayton Water Treatment Resilience Improvements

Public comment ppl listing

loi_id: SD-26-24, revised_on: 2026-06-09

“s (whichever is lower), and interest rates as low as 1%. City of Stayton Issue: Stayton relies on the North Santiam River and slow sand Rating results include: SD-26-24 filtration, downstream of Detroit reservoir. Beginning in winter 2026 5 pts (Health Risk) due to emergency USACE will begin reservoir drawdown operations which can increase intertie with a groundwater source would Marion Arthur Chaput / Michelle Bilberry raw water turbidity elevated sediment load, and organic material provide a secondary source to City of 8,400 which can decrease their filtration and treatment capabilities. Stayton Stayton during USACE Detroit reservoir has an emergency intertie with City of Salem who also relies on the drawdowns. Stayton’s current sources North Santiam River and slow sand filtration and Stayton may not be are surface water and could be heavily able to rely on the intertie during drawdown operations. Stayton needs To be confirmed at the time impacted by future drawdown of invitation to apply and a reliable drinking water source and treatment during the drawdown subject to subsidy operations. operations to provide safe drinking water to customers. 10 pts (Compliance) due to Stayton’s Project: Emergency intertie (bi-directional) with a groundwater source availability. Disadvantaged 2026 slow sand filters are at a high risk of not 22 between Stayton and Sublimity that allows for a different type of Source $2,871,000 $1,435,500 $2,871,000 $1,435,500 communities may qualify (LOI ex”
Portfolio-derived · Stayton Water Treatment Resilience Improvements

Project description

Issue: Stayton relies on the North Santiam River and slow sand filtration, downstream of Detroit reservoir. Beginning in winter 2026 USACE will begin reservoir drawdown operations which can increase raw water turbidity elevated sediment load, and organic material which can decrease their filtration and treatment capabilities. Stayton has an emergency intertie with City of Salem who also relies on the North Santiam River and slow sand filtration and Stayton may not be able to rely on the intertie during drawdown operations. Stayton needs a reliable drinking water source and treatment during the drawdown operations to provide safe drinking water to customers. Project: Emergency intertie (bi-directional) with a groundwater source between Stayton and Sublimity that allows for a different type of drinking water source and for the slow sand plant to be taken offline during drawdown operations.

“Issue: Stayton relies on the North Santiam River and slow sand filtration, downstream of Detroit reservoir. Beginning in winter 2026 USACE will begin reservoir drawdown operations which can increase raw water turbidity elevated sediment load, and organic material which can decrease their filtration and treatment capabilities. Stayton has an emergency intertie with City of Salem who also relies on the North Santiam River and slow sand filtration and Stayton may not be able to rely on the intertie during drawdown operations. Stayton needs a reliable drinking water source and treatment during the drawdown operations to provide safe drinking water to customers. Project: Emergency intertie (bi-directional) with a groundwater source between Stayton and Sublimity that allows for a different type of drinking water source and for the slow sand plant to be taken offline during drawdown operations.”