Tualatin Valley Water District

Reviewed intelligence covers 1 project across design. Current commercial scope concentrates on civil and site work, distribution, and process and controls.

Last verified Oct 9, 2026 1 published project history

Last verified
Oct 9, 2026
Reviewed portfolio
1 project
Source families
3 official families
Historical depth
Unknown

What changed

Highest-value recent account changes

1 published material signal

Reviewed project portfolio

What the owner is planning and building

Published coverage, not a complete capital program

Design / permitting

1
Current position Design Unknown · Procurement forecast
Latest change August staff memo identifies aging Cooper Mountain pump station and replacement project Aug 4, 2026
Confirmed scope Distribution, Pumping and storage, Process and controls, and Civil and site work
Next external milestone Official confirmation of the published summer-2027 bidding forecast and current design/approval status Timing not yet reviewed · Timing unknown
Evidence / exception 2 official source families Last verified Oct 9, 2026

Upcoming external milestones

Next reviewed decision points

Chronological, bounded forecasts
Construction procurement

Confirm the published summer-2027 bidding forecast and current design/approval status

Cooper Mountain Pump Station Replacement and Reservoir 3

Timing
Timing not yet reviewed
Confidence
Timing unknown
Could change timing
Funding status is not established in reviewed records.
Exact official outreach states a summer-2027 bidding forecast. Its publication date is unknown, no formal solicitation is verified, and the August memo/outreach have different late-2028 versus winter-2028–29 completion expectations. The published season remains in the exact forecast text; a current dated milestone window and numerical confidence are not established.

Funding profile

Funding progression by project

No accepted funding record or reviewed funding signal is available.

Procurement and delivery

Reviewed buying position

Organizations and relationships

Documented project-specific roles

Not account-wide incumbency

No consultant, contractor, funding-agency, or partner relationship has been accepted for this portfolio.

Facilities and systems

Commercially relevant public assets

Public information only

No reviewed facility record is available. Waterline IQ does not infer facilities from project names.

Consequential unknowns and conflicts

What current coverage does not establish

Ranked qualification limits
  1. Coverage boundary

    Portfolio completeness is not established

    Current coverage includes published Waterline IQ project histories; it is not a complete capital-program inventory.

  2. Coverage limitation

    Cooper Mountain Pump Station Replacement and Reservoir 3

    Funding and financing amount, authorization and readiness remain unverified; the intertie's budget is separate.

    Open project

Chronological owner activity

Complete reviewed account history

Official event date · newest first
  1. Planning · Project-level

    August staff memo identifies aging Cooper Mountain pump station and replacement project

    The dated TVWD staff memo identifies the same replacement pump station and Reservoir 3 project, explaining resilience and end-of-life needs. Its late-2028 completion expectation is retained as historical planning context. This memo is distinct from the already operating Kemmer intertie and its separate agreement.

    Cooper Mountain Pump Station Replacement and Reservoir 3 · Official evidence

Source coverage and freshness

What Waterline IQ has reviewed

Historical depthUnknown
Official document versions3
Last successful reviewOct 9, 2026
Accepted claims6

OHA published system inventory and selected public-owner refresh

Oregon Health Authority

OperatingLast validated traversal Oct 8, 2026

TVWD manually acquired board publication evidence

Tualatin Valley Water District

Manual evidenceLast validated traversal Unknown

TVWD selected capital-project publication evidence

Tualatin Valley Water District

Manual evidenceLast validated traversal Unknown

Evidence and official sources

Accepted owner and portfolio facts

6 accepted claims
Evidence and material facts — 6 verified claims
Owner fact · Tualatin Valley Water District

Public water system

OR41-00665

“REGION 1 | Washington | 00665 | TUALATIN VALLEY WATER DISTRICT | Active | C | SWP | 224,600 | 62,160 | Residential | Residential | Municipality | | 3 Permanent | 1/1 to 12/31 | RYAN SMITH | 1850 SW 170TH AVE | BEAVERTON, OR 97003 | 971-277-8813 | 4065 | State | Washington1 | EC | SW | P | Residential | Residential | Municipality | N/A | 1Permanent | Year-round | 224600 | 62160”
body:nth-of-type(1) > div#dtTableWrapper:nth-of-type(5) > table#WSTable:nth-of-type(1) > tbody#WSTableBody:nth-of-type(1) > tr:nth-of-type(5002)Published UnknownOfficial source
Owner fact · Tualatin Valley Water District

Water system inventory

county: Washington, pws_id: 00665, status: Active, population: 224,600, connections: 62,160, licensed_by: , system_name: TUALATIN VALLEY WATER DISTRICT, system_type: C, tinwsys_isn: 4065, primary_source: SWP, population_type: Residential, operating_period: 1/1 to 12/31, service_area_type: Municipality, service_area_class: Residential

“REGION 1 | Washington | 00665 | TUALATIN VALLEY WATER DISTRICT | Active | C | SWP | 224,600 | 62,160 | Residential | Residential | Municipality | | 3 Permanent | 1/1 to 12/31 | RYAN SMITH | 1850 SW 170TH AVE | BEAVERTON, OR 97003 | 971-277-8813 | 4065 | State | Washington1 | EC | SW | P | Residential | Residential | Municipality | N/A | 1Permanent | Year-round | 224600 | 62160”
body:nth-of-type(1) > div#dtTableWrapper:nth-of-type(5) > table#WSTable:nth-of-type(1) > tbody#WSTableBody:nth-of-type(1) > tr:nth-of-type(5002)Published UnknownOfficial source
Portfolio-derived · Cooper Mountain Pump Station Replacement and Reservoir 3

Replacement need

TVWD's August 4, 2026 staff memo identifies the aging Cooper Mountain Pump Station, its replacement project and a late-2028 completion expectation. The separate Kemmer intertie is already in service; its IGA and budget are not this project's approval or funding.

“TVWD’s 920 zone is served via direct pumping to service through the Cooper Mountain Pump Station, a single pump station that is nearing the end of its useful life. This pump station is scheduled to be replaced as part of the Cooper Mountain Pump Station Replacement and Reservoir 3 project that is expected to be completed in late 2028.”
Portfolio-derived · Cooper Mountain Pump Station Replacement and Reservoir 3

Project scope

At 18755 SW Kemmer Road: replacement pump station, backup emergency generator, new 2-million-gallon concrete reservoir, connecting underground waterlines, stormwater detention, fencing and landscape. At 18888 SW Kemmer Road: remove the old pump station after new facilities are operational.

“What is the Cooper Mountain Pump Station and Reservoir 3 Project? TVWD is planning improvements to increase the reliability and resilience of the Cooper Mountain water system. The project includes work at two existing TVWD properties: 18755 SW Kemmer Road Construct a new replacement pump station. Install a backup emergency generator. Build a new 2-million-gallon concrete water reservoir. Install underground waterlines connecting the new facilities to the existing water system. Construct a stormwater detention facility. Install new fencing and landscaping. 18888 SW Kemmer Road Remove the existing pump station after the new facilities are operational. What happens next?”
Portfolio-derived · Cooper Mountain Pump Station Replacement and Reservoir 3

Design context

Official outreach describes survey work and field investigations supporting design, explicitly says this is not construction, and lists Design: Summer 2026. The notice's publication date and actual completion of investigations/design remain unknown.

“¿Necesita este aviso en español? Llame al (503) 848-3000 para ayuda con traducción. Dear Neighbor, You are receiving this notice because your property is adjacent to, or shares access with, Tualatin Valley Water District (TVWD) properties located at 18755 and 18888 SW Kemmer Road, where survey work will occur during the week of July 27, 2026. This is not construction. Surveying is one of the first steps in designing the future Cooper Mountain Pump Station and Reservoir 3 Project. Construction is currently anticipated to begin in fall 2027 and is subject to change. Surveying is being completed now so engineers can better understand existing site conditions and develop a design that minimizes impacts on neighboring properties whenever possible. Please see the map below showing the survey area. What should you expect? During the week of July 27, you may see survey crews working weekdays between 7 a.m. and 6 p.m. Most of the work will take place on TVWD property. However, because several neighboring homes share driveways or property boundaries with TVWD, surveyors may also need to work up to 20 feet beyond TVWD’s properties near shared driveways, fence lines, and property corners to accurately determine property boundaries and document existing conditions. You can expect: No interruption to your water service. Surveyors wearing high-visibility safety vests and carrying surveying equipment. Driveways and access to homes will remain open at all times. Individual properties will likely only see survey activity for a short period during the week. No construction or excavation. Temporary paint marks, flags, or stakes used as survey reference points. These help crews complete their work and are not an indication that construction is beginning. Survey vehicles and equipment staged on TVWD property whenever possible. You do not need to be home during the survey. If temporary access near or onto private property is needed to complete a boundary survey or obtain measurements, crews will minimize the time spent there and work respectfully around existing landscaping and improvements. If you have questions or concerns about the temporary markings or survey access near your property, please contact us. We will work with you whenever possible while completing the information needed for project design. Why are surveyors in the area? Surveying is one part of the early design process and is taking place alongside other field investigations, including utility locating, exploratory drilling, and underground utility investigations. The information collected helps engineers: Accurately design the new facilities. Locate existing utilities and property boundaries. Identify potential challenges before construction. Reduce future construction impacts whenever possible. Ensure new facilities are built in the correct location. What is the Cooper Mountain Pump Station and Reservoir 3 Project? TVWD is planning improvements to increase the reliability and resilience of the Cooper Mountain water system. The project includes work at two existing TVWD properties: 18755 SW Kemmer Road Construct a new replacement pump station. Install a backup emergency generator. Build a new 2-million-gallon concrete water reservoir. Install underground waterlines connecting the new facilities to the existing water system. Construct a stormwater detention facility. Install new fencing and landscaping. 18888 SW Kemmer Road Remove the existing pump station after the new facilities are operational. What happens next? The information collected during these field investigations and surveying will be used to complete project design, obtain permits, and prepare for construction. The current project schedule (subject to change) is: Design: Summer 2026 Land Use Review: Fall 2026 Permitting: Spring 2027 Bidding: Summer 2027 Construction Begins: Fall 2027 Project Complete: Winter 2028–29 What will this mean for neighboring properties? We understand that living next to a future construction project can raise questions about traffic, noise, driveway access, and day-to-day activities. Those details are still being developed as part of the design process. The information collected during surveying helps TVWD identify opportunities to reduce impacts wherever possible before construction begins. As the project advances, TVWD will continue working with neighboring property owners and provide regular updates. Before construction starts, we will share information about: Construction schedules and work hours. Expected traffic and driveway impacts. Temporary road or lane closures, if needed. Any anticipated water service interruptions. How to prepare for upcoming work. Opportunities to ask questions and provide feedback. Why are these improvements needed? The Cooper Mountain Pump Station and Reservoir 3 Project will replace aging infrastructure and improve the reliability of the water system serving the Cooper Mountain area. These improvements will strengthen the system during emergencies such as earthquakes and severe weather while continuing to provide safe, reliable drinking water and dependable fire protection for years to come. Questions? Contact TVWD Communications: Call: (503) 848-3000 Email: [email protected] Visit: TVWD.org/Cooper Thank you for your cooperation as we plan to make important improvements to your neighborhood’s water system.”
Portfolio-derived · Cooper Mountain Pump Station Replacement and Reservoir 3

Published milestone forecasts

Subject to change: design summer 2026; land-use review fall 2026; permitting spring 2027; bidding summer 2027; construction fall 2027; completion winter 2028–29. The separate August 4 memo anticipates late 2028; neither original establishes completed milestones or a confirmed current delivery date.

“¿Necesita este aviso en español? Llame al (503) 848-3000 para ayuda con traducción. Dear Neighbor, You are receiving this notice because your property is adjacent to, or shares access with, Tualatin Valley Water District (TVWD) properties located at 18755 and 18888 SW Kemmer Road, where survey work will occur during the week of July 27, 2026. This is not construction. Surveying is one of the first steps in designing the future Cooper Mountain Pump Station and Reservoir 3 Project. Construction is currently anticipated to begin in fall 2027 and is subject to change. Surveying is being completed now so engineers can better understand existing site conditions and develop a design that minimizes impacts on neighboring properties whenever possible. Please see the map below showing the survey area. What should you expect? During the week of July 27, you may see survey crews working weekdays between 7 a.m. and 6 p.m. Most of the work will take place on TVWD property. However, because several neighboring homes share driveways or property boundaries with TVWD, surveyors may also need to work up to 20 feet beyond TVWD’s properties near shared driveways, fence lines, and property corners to accurately determine property boundaries and document existing conditions. You can expect: No interruption to your water service. Surveyors wearing high-visibility safety vests and carrying surveying equipment. Driveways and access to homes will remain open at all times. Individual properties will likely only see survey activity for a short period during the week. No construction or excavation. Temporary paint marks, flags, or stakes used as survey reference points. These help crews complete their work and are not an indication that construction is beginning. Survey vehicles and equipment staged on TVWD property whenever possible. You do not need to be home during the survey. If temporary access near or onto private property is needed to complete a boundary survey or obtain measurements, crews will minimize the time spent there and work respectfully around existing landscaping and improvements. If you have questions or concerns about the temporary markings or survey access near your property, please contact us. We will work with you whenever possible while completing the information needed for project design. Why are surveyors in the area? Surveying is one part of the early design process and is taking place alongside other field investigations, including utility locating, exploratory drilling, and underground utility investigations. The information collected helps engineers: Accurately design the new facilities. Locate existing utilities and property boundaries. Identify potential challenges before construction. Reduce future construction impacts whenever possible. Ensure new facilities are built in the correct location. What is the Cooper Mountain Pump Station and Reservoir 3 Project? TVWD is planning improvements to increase the reliability and resilience of the Cooper Mountain water system. The project includes work at two existing TVWD properties: 18755 SW Kemmer Road Construct a new replacement pump station. Install a backup emergency generator. Build a new 2-million-gallon concrete water reservoir. Install underground waterlines connecting the new facilities to the existing water system. Construct a stormwater detention facility. Install new fencing and landscaping. 18888 SW Kemmer Road Remove the existing pump station after the new facilities are operational. What happens next? The information collected during these field investigations and surveying will be used to complete project design, obtain permits, and prepare for construction. The current project schedule (subject to change) is: Design: Summer 2026 Land Use Review: Fall 2026 Permitting: Spring 2027 Bidding: Summer 2027 Construction Begins: Fall 2027 Project Complete: Winter 2028–29 What will this mean for neighboring properties? We understand that living next to a future construction project can raise questions about traffic, noise, driveway access, and day-to-day activities. Those details are still being developed as part of the design process. The information collected during surveying helps TVWD identify opportunities to reduce impacts wherever possible before construction begins. As the project advances, TVWD will continue working with neighboring property owners and provide regular updates. Before construction starts, we will share information about: Construction schedules and work hours. Expected traffic and driveway impacts. Temporary road or lane closures, if needed. Any anticipated water service interruptions. How to prepare for upcoming work. Opportunities to ask questions and provide feedback. Why are these improvements needed? The Cooper Mountain Pump Station and Reservoir 3 Project will replace aging infrastructure and improve the reliability of the water system serving the Cooper Mountain area. These improvements will strengthen the system during emergencies such as earthquakes and severe weather while continuing to provide safe, reliable drinking water and dependable fire protection for years to come. Questions? Contact TVWD Communications: Call: (503) 848-3000 Email: [email protected] Visit: TVWD.org/Cooper Thank you for your cooperation as we plan to make important improvements to your neighborhood’s water system.”