Wastewater collection Active
Airpark and Waco Sewer Project
Funding applied for (CWSRF); construction expected to start 2027. Next: construction expected during 2027 (forecast).
Last verified Nov 3, 2026 14 official sources
Where does it stand?
Each stage is set from the records below. Stages can overlap.
-
Planning
Done: Identified
Oct 2025 -
Funding
Under way: Applied
May 2026 -
Design
Not settled: Unknown
-
Permitting
Not settled: Unknown
-
Procurement
Not settled: Unknown
-
Construction
Ahead: Forecast
Procurements
Each procurement is a separate public purchase with its own documents, deadline and outcome.
Not yet researched.
What is it?
Design and construction of approximately 1,920 linear feet of pressure sewer main and service laterals serving 22+ properties.
Official scope · 2 statements
- Project scope: Design and construction of approximately 1,920 linear feet of pressure sewer main and service laterals serving 22+ properties. Source
- Project description: This project is part of the City of Bend's Septic to Sewer Conversion program. Project includes design and construction of approximately 1,920 linear feet of pressure sewer main and service laterals, tying into the existing sewer main. The project will allow 22+ properties to decommission septic systems and connect to public sewer supporting water quality protection and helping to eliminate potential public health hazards associated with failing septic systems. Emerging contaminants: Decommissioning septic systems that may contribute PFAS, and other pollutants reduces the risk for discrete conveyance and contamination of groundwater sources and allow for the potential opportunity to centrally collect and treat at a publicly operated treatment facility. Connecting septic systems to centralized sewer systems is progress towards mitigating impacts of emerging contaminants. Source
Waterline IQ interpretation Likely work: Wastewater collection, distribution, and civil and site work
Is it real, and is it funded?
-
$1.59M requested
Requested
Oregon DEQ Clean Water State Revolving Fund, 19470
Source -
Authorization
Authorized
Project selected for design and construction
Oct 27, 2025 -
Authorization
Authorized
Community Building Subcommittee action
Oct 27, 2025 -
Authorization
Authorized
Project selected for design and construction
Oct 27, 2025
What is being bought?
The procurements above, over time. Solid: recorded · dashed: forecast
-
Construction expected during 2027
Official forecast
-
Construction expected during 2027
Official forecast
Who is involved?
- Owner
- City of Bend
- Design / consulting
- Not established
- Funding agencies
- Not established
- Reviewing agencies
- Not established
- Contractors
- Not established
What changed?
What we don't know yet
-
Has the funding been awarded?
Requested funding is documented; no award or executed financing is established.
-
Has it been put out to bid?
Dedicated procurement research has not yet been completed.
-
Who is the design lead?
No accepted project relationship establishes the current design lead.
-
How will it be delivered?
No accepted project decision or procurement record establishes the delivery method.
-
How will the work be packaged?
Potential work is visible, but contract packaging is not established in reviewed records.
-
When will it go out to bid?
Sep 2026–Mar 2027 is a reviewed Waterline IQ forecast, not a confirmed procurement date.
History
- Design
- Funding
- Procurement
- Construction
-
Project selected for design and construction
The Community Building Subcommittee approved the Airpark and Waco area for design and construction.
City of Bend project page -
Community Building Subcommittee action
The subcommittee's public record documents the decision advancing Airpark and Waco into design and construction.
City of Bend meeting minutes -
Project selected for design and construction
The Community Building Subcommittee approved the Airpark and Waco area for design and construction.
City of Bend project page -
CWSRF financing identified
Oregon DEQ listed application 19470 for $1.59 million in design and construction financing.
Oregon DEQ intended use plan -
Design completion and construction procurement Date passed
The City identifies design and construction as approved, with construction scheduled throughout 2027; no formal solicitation date is yet evidenced.
City of Bend project page - Today
-
Construction expected during 2027 Scheduled
The City project page schedules construction throughout 2027.
City of Bend project page -
Construction expected during 2027 Scheduled
The City project page schedules construction throughout 2027.
City of Bend project page
More from the owner
Follow what City of Bend is planning and building next
Five more City of Bend projects, each with its own history, funding and procurements.
6 projects 1 solicitation 1 recent change
City of Bend's whole portfolio, solicitations and recent changes in one place.
- Construction Awbrey Glen and Westside Pump Station Improvements ActiveNo next date published View project
- Design Second Street Waterline Improvements Next: project completion expected by year endDecember 2026, forecast View project
- Funding Denning and Juniperhaven Sewer Project Next: sewer construction expected during 20272027, forecast View project
- +2 Water Reclamation Facility Plan Update and WRF Grit Removal See all projects
Sources
17 accepted claims · 5 official document versions
-
Intended Use Plan 2027, Second Edition Oregon Department of Environmental Quality · retrieved Sep 28, 2026
Inspect exact excerpt View official source
DEQ CWSRF current Intended Use Plan index · PDF page 27
Saved cited excerpt · PDF page 27 “This project is part of the City of Bend's Septic to Sewer Conversion program. Project includes design and construction of approximately 1,920 linear feet of pressure sewer main and service laterals, tying into the existing sewer main. The project will allow 22+ properties to decommission septic systems and connect to public sewer supporting water quality protection and helping to eliminate potential public health hazards associated with failing septic systems. Emerging contaminants: Decommissioning septic systems that may contribute PFAS, and other pollutants reduces the risk for discrete conveyance and contamination of groundwater sources and allow for the potential opportunity to centrally collect and treat at a publicly operated treatment facility. Connecting septic systems to centralized sewer systems is progress towards mitigating impacts of emerging contaminants.”
- Accepted facts
- Project description
- Retrieved
- Sep 28, 2026
- Document hash
d82d4f82838c83723c546c141c0c24abb95e4823af8a64a6286b51264b7dce0f
-
Intended Use Plan 2027, Second Edition Oregon Department of Environmental Quality · retrieved Sep 28, 2026
Inspect exact excerpt View official source
DEQ CWSRF current Intended Use Plan index · PDF page 27
Saved cited excerpt · PDF page 27 “Section 212, Design and Construction, Airpark and Waco Sewer Project.”
- Accepted facts
- Project title
- Retrieved
- Sep 28, 2026
- Document hash
d82d4f82838c83723c546c141c0c24abb95e4823af8a64a6286b51264b7dce0f
-
Intended Use Plan 2027, Second Edition Oregon Department of Environmental Quality · retrieved Sep 28, 2026
Inspect exact excerpt View official source
DEQ CWSRF current Intended Use Plan index · PDF page 27
Saved cited excerpt · PDF page 27 “City of Bend (Deschutes County) Loan application number: 19470 Amount requested: $1,590,000”
- Accepted facts
- Deq cwsrf application, Amount requested, and Funding listing excerpt
- Retrieved
- Sep 28, 2026
- Document hash
d82d4f82838c83723c546c141c0c24abb95e4823af8a64a6286b51264b7dce0f
-
Community Building Subcommittee meeting minutes — October 27, 2025 City of Bend · retrieved Jul 14, 2026
Inspect exact excerpt View official source
Bend Community Building Subcommittee minutes · PDF page 2
Saved cited excerpt · PDF page 2 “into the budget, they will skip it and select the next project that will fit within the budget. Option A would include Airpark Drive, Denning Drive, Waco Drive and Juniperhaven. Option B (Alternative), also factors in the highest-ranking projects, but includes projects that are facilitated by a higher-ranking project. Option B woul”
- Accepted facts
- Committee option a areas
- Supporting records
- Community Building Subcommittee action
- Retrieved
- Jul 14, 2026
- Document hash
17657c39e529c42f49f5d13eebff9f93ff0bacbc63a9d663b843a40c6064d180
-
Airpark and Waco Sewer Project City of Bend · retrieved Jul 14, 2026
Inspect exact excerpt View official source
Bend Airpark and Waco project page · Paragraph on the official webpage
Saved cited excerpt · Paragraph on the official webpage “area to allow approximately 23 properties to decommission their septic systems and connect to the public sewer system. Construction will be completed in phases. Any required Franchise Utility relocation work may begin as early as Summer 2026. The City of Bend Septic to Sewer portion of construction will take place throughout 2027*.”
- Accepted facts
- Construction window
- Supporting records
- Construction expected during 2027
- Retrieved
- Jul 14, 2026
- Publication date
- Dec 16, 2025Publisher-stated page publication date in the preserved source
- Document hash
f7b1c4e03bd95ab6438629a6c8feb789f80fe1cd04ba123d0eb477a9f59823e2
-
Airpark and Waco Sewer Project City of Bend · retrieved Jul 14, 2026
Inspect exact excerpt View official source
Bend Airpark and Waco project page · Paragraph on the official webpage
Saved cited excerpt · Paragraph on the official webpage “This project is funded by the Clean Water State Revolving Fund (CWSRF).”
- Accepted facts
- Funding source
- Retrieved
- Jul 14, 2026
- Publication date
- Dec 16, 2025Publisher-stated page publication date in the preserved source
- Document hash
f7b1c4e03bd95ab6438629a6c8feb789f80fe1cd04ba123d0eb477a9f59823e2
All 14 sources
-
Airpark and Waco Sewer Project City of Bend · retrieved Jul 14, 2026
Inspect exact excerpt View official source
Bend Airpark and Waco project page · List item on the official webpage
Saved cited excerpt · List item on the official webpage “October 27, 2025 – the City of Bend Community Building Subcommittee approved the design and construction of this septic to sewer.”
- Accepted facts
- Owner
- Supporting records
- Project selected for design and construction
- Retrieved
- Jul 14, 2026
- Publication date
- Dec 16, 2025Publisher-stated page publication date in the preserved source
- Document hash
f7b1c4e03bd95ab6438629a6c8feb789f80fe1cd04ba123d0eb477a9f59823e2
-
Airpark and Waco Sewer Project City of Bend · retrieved Jul 14, 2026
Inspect exact excerpt View official source
Bend Airpark and Waco project page · Paragraph on the official webpage
Saved cited excerpt · Paragraph on the official webpage “A Septic to Sewer Conversion Program Project – 1SN10”
- Accepted facts
- Project code
- Retrieved
- Jul 14, 2026
- Publication date
- Dec 16, 2025Publisher-stated page publication date in the preserved source
- Document hash
f7b1c4e03bd95ab6438629a6c8feb789f80fe1cd04ba123d0eb477a9f59823e2
-
CWSRF Intended Use Plan 2027 Oregon Department of Environmental Quality · retrieved Jul 14, 2026
Inspect exact excerpt View official source
DEQ CWSRF Intended Use Plan · PDF page 27
Saved cited excerpt · PDF page 27 “s of emerging contaminants. City of Bend (Deschutes County) Loan application number: 19470 Amount requested: $1,590,000 Section 212, Design and Construction, Airpark and Waco Sewer Project. This project is part of the City of Bend's Septic to Sewer Conversion program. Project includes design and construction of approximately 1,920 linear feet of pressure sewer main and service laterals, tying into the existing sewer main. The project will allow 22+ properties to decommission septic systems and connect to public sewer supporting water quality protection and helping to eliminate potential public health hazards associated with failing sep”
- Accepted facts
- Project scope
- Retrieved
- Jul 14, 2026
- Document hash
42afd8b7b874aea4228fe85968f7dfcf062abe66b82eca28f80d62e0b2b0016f
-
CWSRF Intended Use Plan 2027 Oregon Department of Environmental Quality · retrieved Jul 14, 2026
Inspect exact excerpt View official source
DEQ CWSRF Intended Use Plan · PDF page 27
Saved cited excerpt · PDF page 27 “entralized sewer systems and eliminating pump stations are progress toward mitigating impacts of emerging contaminants. City of Bend (Deschutes County) Loan application number: 19470 Amount requested: $1,590,000 Section 212, Design and Construction, Airpark and Waco Sewer Project. This project is part of the City of Bend's Septic to Sewer Conversion program. Project includes design and co”
- Accepted facts
- CWSRF application number and Funding amount requested
- Supporting records
- CWSRF financing identified
- Retrieved
- Jul 14, 2026
- Document hash
42afd8b7b874aea4228fe85968f7dfcf062abe66b82eca28f80d62e0b2b0016f
-
Airpark and Waco Sewer Project City of Bend · published Dec 16, 2025
Inspect exact excerpt View official source
Bend Airpark and Waco project page · Paragraph on the official webpage
Saved cited excerpt · Paragraph on the official webpage “area to allow approximately 23 properties to decommission their septic systems and connect to the public sewer system. Construction will be completed in phases. Any required Franchise Utility relocation work may begin as early as Summer 2026. The City of Bend Septic to Sewer portion of construction will take place throughout 2027*.”
- Accepted facts
- Construction window
- Supporting records
- Construction expected during 2027
- Retrieved
- Sep 29, 2026
- Publication date
- Dec 16, 2025Saved publication metadata
- Document hash
ae431edeb3373d511958cce30694268d9968009242d015533b5e8853cbdcc432
-
Airpark and Waco Sewer Project City of Bend · published Dec 16, 2025
Inspect exact excerpt View official source
Bend Airpark and Waco project page · Paragraph on the official webpage
Saved cited excerpt · Paragraph on the official webpage “This project is funded by the Clean Water State Revolving Fund (CWSRF).”
- Accepted facts
- Funding source
- Retrieved
- Sep 29, 2026
- Publication date
- Dec 16, 2025Saved publication metadata
- Document hash
ae431edeb3373d511958cce30694268d9968009242d015533b5e8853cbdcc432
-
Airpark and Waco Sewer Project City of Bend · published Dec 16, 2025
Inspect exact excerpt View official source
Bend Airpark and Waco project page · List item on the official webpage
Saved cited excerpt · List item on the official webpage “October 27, 2025 – the City of Bend Community Building Subcommittee approved the design and construction of this septic to sewer.”
- Accepted facts
- Owner
- Supporting records
- Project selected for design and construction
- Retrieved
- Sep 29, 2026
- Publication date
- Dec 16, 2025Saved publication metadata
- Document hash
ae431edeb3373d511958cce30694268d9968009242d015533b5e8853cbdcc432
-
Airpark and Waco Sewer Project City of Bend · published Dec 16, 2025
Inspect exact excerpt View official source
Bend Airpark and Waco project page · Paragraph on the official webpage
Saved cited excerpt · Paragraph on the official webpage “A Septic to Sewer Conversion Program Project – 1SN10”
- Accepted facts
- Project code
- Retrieved
- Sep 29, 2026
- Publication date
- Dec 16, 2025Saved publication metadata
- Document hash
ae431edeb3373d511958cce30694268d9968009242d015533b5e8853cbdcc432