Awbrey Glen and Westside Pump Station Improvements
Address mechanical, electrical, controls, security, access, reliability, safety, and performance deficiencies at both pump stations.
Last verified Sep 25, 2026 2 official source families
Project brief
What is proposed
Address mechanical, electrical, controls, security, access, reliability, safety, and performance deficiencies at both pump stations.
Latest material change
Contract completion targeted
The construction issue summary sets August 2026 as the contract completion date for both pump-station locations.
Commercial scope
Confirmed work and commercial interpretation
What is proposed
Address mechanical, electrical, controls, security, access, reliability, safety, and performance deficiencies at both pump stations.
Potential commercial work
Waterline IQ interpretation of accepted scope. These items are not confirmed contract packages or specifications.
Pumping and storage
Sewage pumps and Emergency generators
Process and controls
Electrical and controls
Civil and site work
Security fencing and access
Wastewater collection
Force main appurtenances
Selected lifecycle
Key official milestones
-
Official event
First pump-station public meeting held
The City held the first of two public meetings for the pump-station improvements.
View evidence for First pump-station public meeting held -
Official event
Notice to proceed anticipated
The issue summary anticipated notice to proceed in January 2025 and construction within four weeks.
View evidence for Notice to proceed anticipated -
Official event
Construction reported underway
The current City project page reports that construction started in early January 2025.
View evidence for Construction reported underway -
Official event
Contract completion targeted
The construction issue summary sets August 2026 as the contract completion date for both pump-station locations.
View evidence for Contract completion targeted
Evidence and sources
15 accepted claims across 2 official document versions
Selected official evidence · Inspect exact excerpts and locators
Awbrey Glen and Westside Pump Station construction award issue summary — December 18, 2024
Bend Awbrey Glen and Westside pump station issue summary“with the Olney construction contractor to reduce impacts to the public. Contract completion date for both pump station locations is August 2026. Budget and Financial Impacts: These expenditures are included in the CIP as 1SPS1 Awbrey Glen and Westside Pump ...”
Awbrey Glen and Westside Pump Station construction award issue summary — December 18, 2024
Bend Awbrey Glen and Westside pump station issue summary“l Impacts: • In accordance with Bend Development Code (BDC) 4.1.215, Public Meetings, the City held two public meetings (one for each pump station) to inform the community of the proposed projects and to receive any concerns associated with the project. • T...”
Awbrey Glen and Westside Pump Station construction award issue summary — December 18, 2024
Bend Awbrey Glen and Westside pump station issue summary“e consistent with the technical nature of the work and current limitations on material acquisition. The Notice to Proceed (NTP) is anticipated to be issued in January 2025 with construction beginning within 4 weeks of NTP. Initial improvements to the Westsi...”
Awbrey Glen and Westside Pump Station Improvements
Bend Awbrey Glen and Westside pump station project page“Construction started in early January of 2025*.”