Willamette Water Treatment Plant

Since clean water is vital to public health, safety and the economy, EWEB is planning to build a second treatment plant on the Willamette River. Water from the new plant would supplement our primary supply and serve as a critical backup should our sole source, the McKenzie River, or sole filtration plant, Hayden Bridge, become unavailable due to a natural or human caused disaster.

Last verified Oct 8, 2026 2 official source families

What is proposed

Since clean water is vital to public health, safety and the economy, EWEB is planning to build a second treatment plant on the Willamette River. Water from the new plant would supplement our primary supply and serve as a critical backup should our sole source, the McKenzie River, or sole filtration plant, Hayden Bridge, become unavailable due to a natural or human caused disaster.

Board approves CM/GC delivery method for Willamette Treatment Plant

The approved August 4 EWEB Board minutes record unanimous 5:0:0 approval to use a Construction Manager/General Contractor for the Willamette Treatment Plant. This authorizes the delivery method; it does not select a contractor or establish a formal response path.

Verified CM/GC solicitation, agency permit decisions and design/cost refinement

Timing is not established in reviewed records.

Confirmed work and commercial interpretation

What is proposed

Since clean water is vital to public health, safety and the economy, EWEB is planning to build a second treatment plant on the Willamette River. Water from the new plant would supplement our primary supply and serve as a critical backup should our sole source, the McKenzie River, or sole filtration plant, Hayden Bridge, become unavailable due to a natural or human caused disaster.

Potential commercial work

Waterline IQ interpretation of accepted scope. These items are not confirmed contract packages or specifications.

Treatment plant

Water treatment plant and Water treatment filtration

Distribution

Transmission water main

Documented permitting

Permit records have not been captured; requirements and approval remain unverified.

Key official milestones

  1. Official event

    October 2021 Board discussion of second-source plant scope

    Board Meeting Presentation - October 2021. Chief Operations Officer, Karen Kelley, and former Water Engineering Supervisor, Wally McCullough, presented information about the treatment plant and associated transmission project to the EWEB Board and heard input on the scope and commitment to fund the project. The first day represents month precision; the original presentation and exact meeting date are not established by this page.

    View evidence for October 2021 Board discussion of second-source plant scope
  2. Official event

    Board approves CM/GC delivery method for Willamette Treatment Plant

    The approved August 4 EWEB Board minutes record unanimous 5:0:0 approval to use a Construction Manager/General Contractor for the Willamette Treatment Plant. This authorizes the delivery method; it does not select a contractor or establish a formal response path.

    View evidence for Board approves CM/GC delivery method for Willamette Treatment Plant
Evidence and sources
4 accepted claims across 4 official document versions
Selected official evidence · Inspect exact excerpts and locators

August 4, 2026 Regular Session (PDF)

EWEB public board publications
Inspect exact excerpt and locator
“President Brown closed the public hearing at 6:51 p.m. Alternative Procurement Process; Use of Construction Manager/General Contractor (CM/GC) Contract [01:18:18] Chief Water Operations Officer Karen Kelley and Principal Water Engineer Laura Farthing respon...”

News Stories

EWEB water reliability project and program publications
Inspect exact excerpt and locator
“Board Meeting Presentation - October 2021. Chief Operations Officer, Karen Kelley, and former Water Engineering Supervisor, Wally McCullough, presented information about the treatment plant and associated transmission project to the EWEB Board and heard inp...”