The scope of work includes: Installing and operating a temporary bypass pumping system. Demolishing and salvaging existing pump station facilities and equipment. Converting the existing caisson into a wet well. Furnishing and installing five submersible pumps, associated piping, three buried concrete vaults, and electrical and instrumentation equipment. Constructing a new above-ground building. Site grading, paving, and grasscrete surfacing construction. Facility startup and testing.

Last verified Oct 12, 2026 1 official source family

What is proposed

The scope of work includes: Installing and operating a temporary bypass pumping system. Demolishing and salvaging existing pump station facilities and equipment. Converting the existing caisson into a wet well. Furnishing and installing five submersible pumps, associated piping, three buried concrete vaults, and electrical and instrumentation equipment. Constructing a new above-ground building. Site grading, paving, and grasscrete surfacing construction. Facility startup and testing.

Header 1. Bid Opening Date changed from "11/02/2023 02:30:00 PM" to "11/08/2023 02:30:00 PM". published

West Irwin Pump Station Replacement: The scope of work includes: Installing and operating a temporary bypass pumping system. Demolishing and salvaging existing pump station facilities and equipment. Converting the existing caisson into a wet well. Furnishing and installing five submersible pumps, associated piping, three buried concrete vaults, and electrical and instrumentation equipment. Constructing a new above-ground building. Site grading, paving, and grasscrete surfacing construction. Facility startup and testing. Responses due 2023-11-29.

Official response deadline

Timing is not established in reviewed records.

Confirmed work and commercial interpretation

What is proposed

The scope of work includes: Installing and operating a temporary bypass pumping system. Demolishing and salvaging existing pump station facilities and equipment. Converting the existing caisson into a wet well. Furnishing and installing five submersible pumps, associated piping, three buried concrete vaults, and electrical and instrumentation equipment. Constructing a new above-ground building. Site grading, paving, and grasscrete surfacing construction. Facility startup and testing.

Potential commercial work

Waterline IQ interpretation of accepted scope. These items are not confirmed contract packages or specifications.

Pumping and storage

Process pumps

Process and controls

Electrical and controls

Documented permitting

Permit records have not been captured; requirements and approval remain unverified.

Key official milestones

  1. Official event

    Official solicitation addendum published

    West Irwin Pump Station Replacement: The official solicitation requests competitive construction bids for West Irwin Pump Station Replacement. Responses due 2023-11-29.

    View evidence for Official solicitation addendum published
  2. Official event

    Official solicitation scope changed

    West Irwin Pump Station Replacement: The scope of work includes: Installing and operating a temporary bypass pumping system. Demolishing and salvaging existing pump station facilities and equipment. Converting the existing caisson into a wet well. Furnishing and installing five submersible pumps, associated piping, three buried concrete vaults, and electrical and instrumentation equipment. Constructing a new above-ground building. Site grading, paving, and grasscrete surfacing construction. Facility startup and testing. Responses due 2023-11-29.

    View evidence for Official solicitation scope changed
  3. Official event

    Header 1. Bid Opening Date changed from "11/02/2023 02:30:00 PM" to "11/08/2023 02:30:00 PM". published

    West Irwin Pump Station Replacement: The scope of work includes: Installing and operating a temporary bypass pumping system. Demolishing and salvaging existing pump station facilities and equipment. Converting the existing caisson into a wet well. Furnishing and installing five submersible pumps, associated piping, three buried concrete vaults, and electrical and instrumentation equipment. Constructing a new above-ground building. Site grading, paving, and grasscrete surfacing construction. Facility startup and testing. Responses due 2023-11-29.

    View evidence for Header 1. Bid Opening Date changed from "11/02/2023 02:30:00 PM" to "11/08/2023 02:30:00 PM". published
Evidence and sources
1 accepted claims across 3 official document versions
Selected official evidence · Inspect exact excerpts and locators

Eugene West Irwin pump station replacement

OregonBuys water-infrastructure outcome discovery
Inspect exact excerpt and locator
“Bid Number: S-KE0010-00008406 Description: ITB 25 West Irwin Pump Station Replacement Bid Opening Date: 11/29/2023 02:30:00 PM Purchaser: Milissa Bateman Organization: City of Eugene Department: KE001004 - Engineering Location: KE001 - Engineering Fiscal Ye...”

Eugene West Irwin pump station replacement

OregonBuys water-infrastructure outcome discovery
Inspect exact excerpt and locator
“Bid Solicitation: S-KE0010-00008406 Header Information Bid Number: S-KE0010-00008406 Description: ITB 25 West Irwin Pump Station Replacement Bid Opening Date: 11/29/2023 02:30:00 PM Purchaser: Milissa Bateman Organization: City of Eugene Department: KE00100...”

Eugene West Irwin pump station replacement

OregonBuys water-infrastructure outcome discovery
Inspect exact excerpt and locator
“The scope of work includes: Installing and operating a temporary bypass pumping system. Demolishing and salvaging existing pump station facilities and equipment. Converting the existing caisson into a wet well. Furnishing and installing five submersible pum...”

Eugene West Irwin pump station replacement

OregonBuys water-infrastructure outcome discovery
Inspect exact excerpt and locator
“New File Attachments: 975215 Addendum 5 975215 Intent to Award 975215 Bid Tabulation 975215 First Tier Subcontractor 975215 Instructions to Bidders 975215 Contract and Bonds 975215 Bid Forms 975215 Specifications 975215 Plans 1 of 7 975215 Plans 2 of 7 9752...”