Fulton Pump Main Replacement
This project will install approximately 3,350 feet of new 20-inch pump main, including a 230-foot section bored under the I-5 freeway and a 210-foot section bored under SW Barbur Blvd. The project will include abandoning approximately 3,180 feet of 10-inch pump main and 3,180 feet of 12-inch pump main between the I-5 right-of-way and the Burlingame Tank Site. In FY 26-27, project will continue construction.
Last verified Oct 9, 2026 3 official source families
Project brief
What is proposed
This project will install approximately 3,350 feet of new 20-inch pump main, including a 230-foot section bored under the I-5 freeway and a 210-foot section bored under SW Barbur Blvd. The project will include abandoning approximately 3,180 feet of 10-inch pump main and 3,180 feet of 12-inch pump main between the I-5 right-of-way and the Burlingame Tank Site. In FY 26-27, project will continue construction.
Latest material change
Fulton update reports pipe installation and drilling complete; other work continues
The section explicitly marked Last updated September 16, 2026 reports new pipes installed and underground drilling complete while work continues in small areas. This is the section's stated update date, not an independently verified upload date or whole-project completion. Connection/cleanup descriptions elsewhere in the page require current confirmation.
Commercial scope
Confirmed work and commercial interpretation
What is proposed
This project will install approximately 3,350 feet of new 20-inch pump main, including a 230-foot section bored under the I-5 freeway and a 210-foot section bored under SW Barbur Blvd. The project will include abandoning approximately 3,180 feet of 10-inch pump main and 3,180 feet of 12-inch pump main between the I-5 right-of-way and the Burlingame Tank Site. In FY 26-27, project will continue construction.
Potential commercial work
Waterline IQ interpretation of accepted scope. These items are not confirmed contract packages or specifications.
Distribution
Water main replacement and Valves and appurtenances
Civil and site work
Trenching and restoration and Traffic control
Permits and approvals
Documented permitting
Permit records have not been captured; requirements and approval remain unverified.
Selected lifecycle
Key official milestones
-
Official event
Council passes Fulton construction-solicitation authorization
Ordinance 191081 authorizes solicitation; contract execution is conditional on Council acceptance of a recommended bidder report and approval of contract form. This original does not name a winning contractor or establish an executed award.
View evidence for Council passes Fulton construction-solicitation authorization -
Official event
Fulton update reports pipe installation and drilling complete; other work continues
The section explicitly marked Last updated September 16, 2026 reports new pipes installed and underground drilling complete while work continues in small areas. This is the section's stated update date, not an independently verified upload date or whole-project completion. Connection/cleanup descriptions elsewhere in the page require current confirmation.
View evidence for Fulton update reports pipe installation and drilling complete; other work continues
Evidence and sources
6 accepted claims across 3 official document versions
Selected official evidence · Inspect exact excerpts and locators
Fulton Pump main replacement
Portland Water Bureau project publication discovery“We have installed all of the new water pipes along the project route. All underground drilling is complete. Work is still continuing in small areas along these roads.”
Portland Water selected historical Council evidence
Portland Water selected historical Council evidence“Passed by Council November 30, 2022”