WRF Grit Removal
A programmed City of Bend capital project to add grit-removal capability at the Water Reclamation Facility.
Last verified Sep 25, 2026 2 official source families
Project brief
What is proposed
A programmed City of Bend capital project to add grit-removal capability at the Water Reclamation Facility.
Latest material change
Initial capital-program funding year begins
The adopted five-year program schedules $750,000 in FY2025-26, $3 million in FY2026-27, and $2 million in FY2027-28.
Commercial scope
Confirmed work and commercial interpretation
What is proposed
A programmed City of Bend capital project to add grit-removal capability at the Water Reclamation Facility.
Potential commercial work
Waterline IQ interpretation of accepted scope. These items are not confirmed contract packages or specifications.
Pumping and storage
Process pumps
Process and controls
Grit removal system, Grit classifier and conveyance, Process piping and valves, and Electrical and controls
Civil and site work
Concrete and structural
Selected lifecycle
Key official milestones
-
Official event
City Council adopts the five-year capital program
The Council resolution adopts the 2026-2030 Capital Improvement Programs, whose incorporated exhibit identifies project 1SWGR.
View evidence for City Council adopts the five-year capital program -
Official event
Initial capital-program funding year begins
The adopted five-year program schedules $750,000 in FY2025-26, $3 million in FY2026-27, and $2 million in FY2027-28.
View evidence for Initial capital-program funding year begins
Evidence and sources
6 accepted claims across 2 official document versions
Selected official evidence · Inspect exact excerpts and locators
Resolution adopting 2026-2030 Capital Improvement Programs — June 18, 2025
Bend resolution adopting the 2026-2030 Capital Improvement Programs“RESOLUTION NO. A RESOLUTION OF THE CITY COUNCIL ADOPTING THE 2026-2030 CAPITAL IMPROVEMENT PROGRAMS Findings: A. The City’s Fiscal Policies state that a five-year Capital Improvement Program (CIP) encompassing all City facilities shall be prepared and updat...”
Exhibit A — 2026-2030 Capital Improvement Programs
Bend 2026-2030 Capital Improvement Program exhibit“1SSFU - Support Facilities Upgrade 5 - 500,000 500,000 - - 1,000,000 1SSW3 - SW Sewer Basin Improvements Phase 3 5 1,325,000 5,100,000 1,700,000 - - 8,125,000 1SWGR - WRF Grit Removal 5 750,000 3,000,000 2,000,000 - - 5,750,000 1TABB - Archie Briggs Bridge ...”