City of Bend
Reviewed intelligence covers 5 projects across construction, design, and planning. Current commercial scope concentrates on civil and site work, wastewater collection, and distribution.
Last verified Sep 25, 2026 5 published project histories
- Last verified
- Sep 25, 2026
- Reviewed portfolio
- 5 projects
- Source families
- 10 official families
- Historical depth
- 2022
Account brief
Current reviewed account position
Current Waterline IQ coverage includes 5 published project histories across construction, design / permitting, and need / planning. Accepted project records cover drinking water and wastewater, with reviewed work concentrated in civil and site work, wastewater collection, distribution, and process and controls. This is a portfolio-derived account view, not a complete capital-program, staffing, facility, or procurement inventory.
- Published projects
- 5
- Official source families
- 10
- Lifecycle breadth
- 3 stages
- Recent material changes
- 2
- Nearest external milestone
- Jul 2026–Mar 2027
What changed
Highest-value recent account changes
-
Completion
Contract completion targeted
Completion adds owner and competitor history but usually closes the current pursuit window.
Awbrey Glen and Westside Pump Station Improvements · August 2026 -
Utility relocation
Franchise utility relocation may begin
The revised sequence changes when sellers should qualify and mobilize.
Denning and Juniperhaven Sewer Project · July 2026 -
Public information
Pre-construction open house held
Active delivery changes near-term demand and closes the primary pursuit window.
Second Street Waterline Improvements · Jun 25, 2026 -
Funding
CWSRF financing identified
Design and franchise-utility coordination are advancing before 2027 construction, but official records disagree on the pipe system. That uncertainty changes the supplier, equipment, and installation opportunity and must remain explicit.
Denning and Juniperhaven Sewer Project · May 12, 2026
Reviewed project portfolio
What the owner is planning and building
Need / planning
1Design / permitting
2Construction
2Upcoming external milestones
Next reviewed decision points
Franchise utility relocation followed by sewer construction
Denning and Juniperhaven Sewer Project
- Timing
- Jul 2026–Mar 2027
- Confidence
- Moderate confidence
- Could change timing
- Official records disagree on whether the planned sewer main is pressure or gravity sewer.
Complete phased installation and place the upsized main in service
Second Street Waterline Improvements
- Timing
- Jul 2026–Dec 2026
- Confidence
- High confidence
- Could change timing
- Unknown funding is documented; no award or executed financing is established.
Define the grit-removal alternative and advance design or procurement
- Timing
- Jul 2026–Jun 2027
- Confidence
- Moderate confidence
- Could change timing
- Unknown funding is documented; no award or executed financing is established.
Design completion and construction procurement
Airpark and Waco Sewer Project
- Timing
- Sep 2026–Mar 2027
- Confidence
- Moderate confidence
- Could change timing
- Requested funding is documented; no award or executed financing is established.
Funding profile
Funding progression by project
Airpark and Waco Sewer Project
Requested · $1,590,000 requested
No award confirmed- Programs
- Oregon DEQ Clean Water State Revolving Fund
- Remaining funding gap
- Not established
Awbrey Glen and Westside Pump Station Improvements
Awarded
Awarded funding confirmed- Programs
- Clean Water State Revolving Fund, Oregon DEQ Clean Water State Revolving Fund loan, and Clean Water State Revolving Fund (CWSRF)
- Remaining funding gap
- Not established
Denning and Juniperhaven Sewer Project
Requested · $2,000,000 requested
No award confirmed- Programs
- Oregon DEQ Clean Water State Revolving Fund
- Remaining funding gap
- Not established
Procurement and delivery
Reviewed buying position
Airpark and Waco Sewer Project
Not yet researched
No formal solicitation identified in reviewed records; dedicated procurement research is not complete.
Awbrey Glen and Westside Pump Station Improvements
Awarded procurement
- Method
- Competitive low bid
- Advertised
- Oct 24, 2024
- Bid portal
- Bonfire
Denning and Juniperhaven Sewer Project
Not yet researched
No formal solicitation identified in reviewed records; dedicated procurement research is not complete.
Second Street Waterline Improvements
Procurement details incomplete
Procurement details incomplete
WRF Grit Removal
Not yet researched
No formal solicitation identified in reviewed records; dedicated procurement research is not complete.
Organizations and relationships
Documented project-specific roles
Funding agency
- Oregon Department of Environmental QualityAwbrey Glen and Westside Pump Station ImprovementsEvidence
Contractor
- Emery & Sons Construction Group, LLCAwbrey Glen and Westside Pump Station ImprovementsEvidence
Facilities and systems
Commercially relevant public assets
Awbrey Glen Pump Station
Wastewater pump station
Related projects: Awbrey Glen and Westside Pump Station ImprovementsWestside Pump Station
Wastewater pump station
Related projects: Awbrey Glen and Westside Pump Station ImprovementsConsequential unknowns and conflicts
What current coverage does not establish
-
Coverage boundary
Portfolio completeness is not established
Current coverage includes published Waterline IQ project histories; it is not a complete capital-program inventory.
-
Procurement research
Airpark and Waco Sewer Project: procurement has not yet been researched
No conclusion about solicitation timing, delivery method, or procurement status should be drawn from current coverage.
Open project -
Funding position
Airpark and Waco Sewer Project: no award or executed financing is established
No award confirmed
Open project -
Procurement research
Denning and Juniperhaven Sewer Project: procurement has not yet been researched
No conclusion about solicitation timing, delivery method, or procurement status should be drawn from current coverage.
Open project -
Funding position
Denning and Juniperhaven Sewer Project: no award or executed financing is established
No award confirmed
Open project -
Coverage limitation
Second Street Waterline Improvements
Procurement evidence is incomplete in the reviewed source set.
Open project -
Procurement research
WRF Grit Removal: procurement has not yet been researched
No conclusion about solicitation timing, delivery method, or procurement status should be drawn from current coverage.
Open project -
Reviewed conflict
Denning and Juniperhaven Sewer Project: Project scope disputed
Gravity and pressure sewer systems imply materially different pipe, pumping, electrical, controls, manhole, installation, subcontractor, and manufacturer requirements. Treating either system as settled could misdirect seller outreach and qualification.
Open project
Chronological owner activity
Complete reviewed account history
-
Completion · Project-level
Contract completion targeted
The construction issue summary sets August 2026 as the contract completion date for both pump-station locations.
Awbrey Glen and Westside Pump Station Improvements · Official evidence -
Utility relocation · Project-level
Franchise utility relocation may begin
The City says required natural-gas, power, or communications relocation may begin as early as summer 2026.
Denning and Juniperhaven Sewer Project · Official evidence -
Public information · Project-level
Pre-construction open house held
The City hosted a public open house to present the construction schedule and anticipated impacts.
Second Street Waterline Improvements · Official evidence -
Funding · Project-level
CWSRF financing identified
Oregon DEQ listed application 31695 for $2 million in design and construction financing.
Denning and Juniperhaven Sewer Project · Official evidence -
Funding · Project-level
CWSRF financing identified
Oregon DEQ listed application 19470 for $1.59 million in design and construction financing.
Airpark and Waco Sewer Project · Official evidence -
Baseline history · Project-level
Project selected for design and construction
The Community Building Subcommittee approved Denning Drive and Juniperhaven for design and construction.
Denning and Juniperhaven Sewer Project · Official evidence -
Baseline history · Project-level
Community Building Subcommittee action
The subcommittee's public record includes Denning Drive and Juniperhaven in the selected Option A program areas.
Denning and Juniperhaven Sewer Project · Official evidence -
Baseline history · Project-level
Project selected for design and construction
The Community Building Subcommittee approved the Airpark and Waco area for design and construction.
Airpark and Waco Sewer Project · Official evidence -
Baseline history · Project-level
Community Building Subcommittee action
The subcommittee's public record documents the decision advancing Airpark and Waco into design and construction.
Airpark and Waco Sewer Project · Official evidence -
Baseline history · Project-level
Initial capital-program funding year begins
The adopted five-year program schedules $750,000 in FY2025-26, $3 million in FY2026-27, and $2 million in FY2027-28.
WRF Grit Removal · Official evidence -
Baseline history · Project-level
City Council adopts the five-year capital program
The Council resolution adopts the 2026-2030 Capital Improvement Programs, whose incorporated exhibit identifies project 1SWGR.
WRF Grit Removal · Official evidence -
Baseline history · Project-level
Notice to proceed anticipated
The issue summary anticipated notice to proceed in January 2025 and construction within four weeks.
Awbrey Glen and Westside Pump Station Improvements · Official evidence -
Baseline history · Project-level
Construction contract authorized
City Council authorized the Emery & Sons construction contract and amendment authority.
Awbrey Glen and Westside Pump Station Improvements · Official evidence -
Baseline history · Project-level
Three construction bids received
Emery & Sons submitted the lowest responsible and responsive bid at $5,742,480.
Awbrey Glen and Westside Pump Station Improvements · Official evidence -
Baseline history · Project-level
Construction solicitation advertised
The City advertised the competitive low-bid construction documents on its Bonfire platform.
Awbrey Glen and Westside Pump Station Improvements · Official evidence -
Baseline history · Project-level
First pump-station public meeting held
The City held the first of two public meetings for the pump-station improvements.
Awbrey Glen and Westside Pump Station Improvements · Official evidence
Source coverage and freshness
What Waterline IQ has reviewed
Bend 2026-2030 Capital Improvement Program exhibit
City of Bend
Bend Airpark and Waco project page
City of Bend
Bend Awbrey Glen and Westside pump station issue summary
City of Bend
Bend Awbrey Glen and Westside pump station project page
City of Bend
Bend Community Building Subcommittee minutes
City of Bend
Bend Denning and Juniperhaven project page
City of Bend
Bend resolution adopting the 2026-2030 Capital Improvement Programs
City of Bend
Bend Second Street Waterline open-house exhibits
City of Bend
Bend Second Street Waterline project page
City of Bend
DEQ CWSRF Intended Use Plan
Oregon Department of Environmental Quality
Evidence and official sources
Accepted owner and portfolio facts
Evidence and material facts — 47 verified claims
Organization governance type
city_municipality
“City of Bend”
CWSRF application number
19470
“entralized sewer systems and eliminating pump stations are progress toward mitigating impacts of emerging contaminants. City of Bend (Deschutes County) Loan application number: 19470 Amount requested: $1,590,000 Section 212, Design and Construction, Airpark and Waco Sewer Project. This project is part of the City of Bend's Septic to Sewer Conversion program. Project includes design and co”
Funding amount requested
$1,590,000 USD
“entralized sewer systems and eliminating pump stations are progress toward mitigating impacts of emerging contaminants. City of Bend (Deschutes County) Loan application number: 19470 Amount requested: $1,590,000 Section 212, Design and Construction, Airpark and Waco Sewer Project. This project is part of the City of Bend's Septic to Sewer Conversion program. Project includes design and co”
Project scope
Design and construction of approximately 1,920 linear feet of pressure sewer main and service laterals serving 22+ properties.
“s of emerging contaminants. City of Bend (Deschutes County) Loan application number: 19470 Amount requested: $1,590,000 Section 212, Design and Construction, Airpark and Waco Sewer Project. This project is part of the City of Bend's Septic to Sewer Conversion program. Project includes design and construction of approximately 1,920 linear feet of pressure sewer main and service laterals, tying into the existing sewer main. The project will allow 22+ properties to decommission septic systems and connect to public sewer supporting water quality protection and helping to eliminate potential public health hazards associated with failing sep”
Construction window
2027
“area to allow approximately 23 properties to decommission their septic systems and connect to the public sewer system. Construction will be completed in phases. Any required Franchise Utility relocation work may begin as early as Summer 2026. The City of Bend Septic to Sewer portion of construction will take place throughout 2027*.”
Funding source
Oregon DEQ Clean Water State Revolving Fund
“This project is funded by the Clean Water State Revolving Fund (CWSRF).”
Owner
City of Bend
“October 27, 2025 – the City of Bend Community Building Subcommittee approved the design and construction of this septic to sewer.”
Project code
1SN10
“A Septic to Sewer Conversion Program Project – 1SN10”
Committee option a areas
Airpark Drive, Denning Drive, Waco Drive, Juniperhaven
“into the budget, they will skip it and select the next project that will fit within the budget. Option A would include Airpark Drive, Denning Drive, Waco Drive and Juniperhaven. Option B (Alternative), also factors in the highest-ranking projects, but includes projects that are facilitated by a higher-ranking project. Option B woul”
Owner
City of Bend
“Pump Station Project (1SPS1). Staff Member, Department: Lisa M. Cameli, PE, Engineering Department Meeting Date: 12/18/2024 Action(s) Required: ☐ Consent Agenda ☐Ordinance First Reading ☐Public Hearing ☐Information/Direction ☐Ordinance Second Reading ☐Resolution ☒ Motion Recommended Motion: I move to authorize a Construction Contract with Emery & Sons Construction Group, LLC, in substantially the form presented to Council, for construction of the Awbrey Glen and Westside Pump Station Improvements Project in an amount not to exceed $5,742,480 and to authorize the City Manager to approve contract amendments up to $575,000. Issue / Council Decision & Discussion Points: • Emery & Sons Construction Group, LLC, was selected through a formal procurement process in accordance with the”
Project code
1SPS1
“Pump Station Project (1SPS1). Staff Member, Department: Lisa M. Cameli, PE, Engineering Department Meeting Date: 12/18/2024 Action(s) Required: ☐ Consent Agenda ☐Ordinance First Reading ☐Public Hearing ☐Information/Direction ☐Ordinance Second Reading ☐Resolution ☒ Motion Recommended Motion: I move to authorize a Construction Contract with Emery & Sons Construction Group, LLC, in substantially the form presented to Council, for construction of the Awbrey Glen and Westside Pump Station Improvements Project in an amount not to exceed $5,742,480 and to authorize the City Manager to approve contract amendments up to $575,000. Issue / Council Decision & Discussion Points: • Emery & Sons Construction Group, LLC, was selected through a formal procurement process in accordance with the”
Construction contractor
Emery & Sons Construction Group, LLC
“Pump Station Project (1SPS1). Staff Member, Department: Lisa M. Cameli, PE, Engineering Department Meeting Date: 12/18/2024 Action(s) Required: ☐ Consent Agenda ☐Ordinance First Reading ☐Public Hearing ☐Information/Direction ☐Ordinance Second Reading ☐Resolution ☒ Motion Recommended Motion: I move to authorize a Construction Contract with Emery & Sons Construction Group, LLC, in substantially the form presented to Council, for construction of the Awbrey Glen and Westside Pump Station Improvements Project in an amount not to exceed $5,742,480 and to authorize the City Manager to approve contract amendments up to $575,000. Issue / Council Decision & Discussion Points: • Emery & Sons Construction Group, LLC, was selected through a formal procurement process in accordance with the”
Construction contract
$5,742,480 USD
“Pump Station Project (1SPS1). Staff Member, Department: Lisa M. Cameli, PE, Engineering Department Meeting Date: 12/18/2024 Action(s) Required: ☐ Consent Agenda ☐Ordinance First Reading ☐Public Hearing ☐Information/Direction ☐Ordinance Second Reading ☐Resolution ☒ Motion Recommended Motion: I move to authorize a Construction Contract with Emery & Sons Construction Group, LLC, in substantially the form presented to Council, for construction of the Awbrey Glen and Westside Pump Station Improvements Project in an amount not to exceed $5,742,480 and to authorize the City Manager to approve contract amendments up to $575,000. Issue / Council Decision & Discussion Points: • Emery & Sons Construction Group, LLC, was selected through a formal procurement process in accordance with the”
Authorized contract amendments
$575,000 USD
“Pump Station Project (1SPS1). Staff Member, Department: Lisa M. Cameli, PE, Engineering Department Meeting Date: 12/18/2024 Action(s) Required: ☐ Consent Agenda ☐Ordinance First Reading ☐Public Hearing ☐Information/Direction ☐Ordinance Second Reading ☐Resolution ☒ Motion Recommended Motion: I move to authorize a Construction Contract with Emery & Sons Construction Group, LLC, in substantially the form presented to Council, for construction of the Awbrey Glen and Westside Pump Station Improvements Project in an amount not to exceed $5,742,480 and to authorize the City Manager to approve contract amendments up to $575,000. Issue / Council Decision & Discussion Points: • Emery & Sons Construction Group, LLC, was selected through a formal procurement process in accordance with the”
Project scope
Address mechanical, electrical, controls, security, access, reliability, safety, and performance deficiencies at both pump stations.
“to “ensure water, wastewater, and stormwater systems are aligned with the needs of a growing city.” The purpose of the Project is to improve the condition, reliability, and safety of the Awbrey Glen and Westside Pump Stations. This project will address mechanical, electrical, system controls, security, access, and performance deficiencies. The Project includes installation of new pumps, generators, a dedicated backup system, automatic transfer switch, driveway access improvements, fencing, and mechanical, electrical, and control equipment. This project was identified in the 2014 Collection System Master Plan (CSMP). It is identified in the CSMP as a Lift Station Upgrade Improvement Project (CSMP”
Facility operations
Awbrey Glen processes about 120,000 gallons per day; Westside conveys about 850,000 gallons per day and is adjacent to the Deschutes River.
“ified as Project ID 31 and 131 in the CSMP Capital Improvement Project List (CSMP pages 157 & 173). The Awbrey Glen Pump Station is located on the Awbrey Glen Golf Course property at 2540 NW Champion Circle within an existing easement and Putnam Road right of way. The pump station processes approximately 120,000 gallons of sewage per day. The pump station was constructed in 1992, and improvements are needed to increase worker safety, comply with current code, and improve the efficiency of the pump station. The Westside Pump Station is located at 35 NW Portland Avenue and is one of the largest pump stations in Bend. It is immediately adjacent to the Deschutes River and conveys approximately 850,000 gallons of sewage per day. The pump station was originally constructed in 1980, with significant improvements completed in 2005. Additional improvements are needed to increase safety, reliability, and redundancy to improve worker safety and to prevent potential sanitary sewer overflows into the river. To improve resiliency and maintenance access of the existing 16” force main, the City is adding control valving, a pig port (used for force main cleaning), and the components to more easily bypass the force main in the case of emergency. The Contractor was selected through a competitive low-bid process. The bid documents were advertised on the City’s Bonfire platform on October 24, 2024. Three”
Funding source
Oregon DEQ Clean Water State Revolving Fund loan
“procurement process in accordance with the City’s Municipal Code Chapter 1.55, Public Contracts. • This project is funded via a loan from the Oregon Department of Environmental Quality (DEQ) under the Clean Water State Revolving Fund (CWSRF). The current DEQ loan amount is $5,310,000. The City is in the process of requesting additional loan funding to cover the total anticipated project costs. • City Manager amendment authority is requested to cover potential construction cost change orders in the amount of 10% of the original contract price. Add bu”
CWSRF loan at award
$5,310,000 USD
“procurement process in accordance with the City’s Municipal Code Chapter 1.55, Public Contracts. • This project is funded via a loan from the Oregon Department of Environmental Quality (DEQ) under the Clean Water State Revolving Fund (CWSRF). The current DEQ loan amount is $5,310,000. The City is in the process of requesting additional loan funding to cover the total anticipated project costs. • City Manager amendment authority is requested to cover potential construction cost change orders in the amount of 10% of the original contract price. Add bu”
Project purpose
Electrical and pump improvements at the Awbrey Glen and Westside wastewater lift stations.
“This project will provide needed electrical and pump improvements at two locations – Awbrey Glen Lift Station and Westside Lift Station.”
Westside scope
Mechanical and electrical upgrades, a backup pump system, driveway improvements, security fencing, and landscaping.
“The City of Bend is beginning design for improvements to the Westside sewer pump station located at 35 NW Portland Avenue (see map below). The project will include mechanical and electrical upgrades, construction of a backup pump system, driveway improvements, security fencing, and landscaping. This project will increase the station’s safety and reliability.”
Awbrey glen scope
A 200-square-foot electrical controls building, emergency generator, paving, and landscaping.
“The City of Bend has started design for improvements to the Awbrey Glen sewer pump station located along Putnam Road at the Awbrey Glen Golf Course (see map below). The project will include construction of a 200 square feet electrical controls building, a new emergency generator and additional paving and landscaping. This project will improve the pump station’s safety and reliability.”
Westside location
35 NW Portland Avenue
“Westside Sewer Pump Station: location at 35 NW Portland Avenue”
Awbrey glen location
Putnam Road at the Awbrey Glen Golf Course
“Awbrey Glen Sewer Pump Station: location at Putnam Road at the Awbrey Glen Golf Course”
Funding source
Clean Water State Revolving Fund (CWSRF)
“This project is funded by the Clean Water State Revolving Fund (CWSRF)”
Construction window
2027
“area to allow approximately 24 properties to decommission their septic systems and connect to the public sewer system. Construction will be completed in phases. Any required Franchise Utility relocation work may begin as early as Summer 2026. The City of Bend Septic to Sewer portion of construction will take place throughout 2027*.”
Funding source
Oregon DEQ Clean Water State Revolving Fund
“This project is funded by the Clean Water State Revolving Fund (CWSRF).”
Owner
City of Bend
“On October 27, 2025, the City of Bend Community Building Subcommittee approved this project.”
Project code
1SN11
“Septic to Sewer Program Project – 1SN11”
Project scope
Gravity sewer mains and service laterals will serve approximately 24 properties in the Denning Drive and Juniperhaven areas.
“Gravity sewer mains will be constructed in each of the application areas. Sewer laterals will be installed to every tax lot in the area to allow approximately 24 properties to decommission their septic systems and connect to the public sewer system. Construction will be completed in phases. Any required Franchise Utility relocation work may begin as”
CWSRF application number
31695
“tralized sewer systems is progress towards mitigating impacts of emerging contaminants. City of Bend (Deschutes County) Loan application number: 31695 Amount requested: $2,000,000 Section 212, Design and Construction, Denning and Juniperhaven Sewer Project. This project is part of the City of Bend's Septic to Sewer Conversion program. Project includes desig”
Funding amount requested
$2,000,000 USD
“tralized sewer systems is progress towards mitigating impacts of emerging contaminants. City of Bend (Deschutes County) Loan application number: 31695 Amount requested: $2,000,000 Section 212, Design and Construction, Denning and Juniperhaven Sewer Project. This project is part of the City of Bend's Septic to Sewer Conversion program. Project includes desig”
Project scope
Design and construction of approximately 2,085 linear feet of pressure sewer main and service laterals serving 24+ properties.
“s of emerging contaminants. City of Bend (Deschutes County) Loan application number: 31695 Amount requested: $2,000,000 Section 212, Design and Construction, Denning and Juniperhaven Sewer Project. This project is part of the City of Bend's Septic to Sewer Conversion program. Project includes design and construction of approximately 2,085 linear feet of pressure sewer main and service laterals, tying into the existing sewer main. The project will allow 24+ properties to decommission septic systems and connect to public sewer supporting water quality protection and helping to eliminate potential public health hazards associated with failing sep”
Committee option a areas
Airpark Drive, Denning Drive, Waco Drive, Juniperhaven
“air. Findley then shared a graph showing how the applications are ultimately scored. Suhr provided two recommendations, Option A (Traditional), which includes as many applications as possible, starting with the highest ranking and moving down the list, that will fit within the annual budget of $3.5 million. If a project doesn’t fit into the budget, they will skip it and select the next project that will fit within the budget. Option A would include Airpark Drive, Denning Drive, Waco Drive and Juniperhaven. Option B (Alternative), also factors in the highest-ranking projects, but includes projects that are facilitated by a higher-ranking project. Option B would include Airpark Drive”
Project scope
Replace the existing 12-inch cast iron water main with an 18-inch ductile iron water main to increase capacity and system resilience.
“This project will replace the existing 12-inch cast iron water main with 18-inch ductile iron water main. The pipe replacement and upsizing will increase capacity from Awbrey Reservoir to Pilot Butte Reservoir, and improve system resilience.”
Construction window
July through November 2026
“Construction – July through November 2026”
Funding source
City of Bend water utility rates under the Water Capital Repair and Replacement Program
“This project is funded by water utility rates under the Water Capital Repair and Replacement Program.”
Owner
City of Bend
“The City of Bend hosted a pre-construction open house on June 25 for the Second Street Waterline Project, inviting the public to meet the project team, ask questions, and learn about the construction schedule and anticipated impacts.”
System purpose
Modernize and connect water infrastructure between Awbrey Butte and Pilot Butte to improve resilience, capacity, and reliability.
“SECOND STREET WA TERLINE PROJECT Strengthening Bend’s Water System The Second Street Waterline Project segment continues the momentum is part of a planned effort to by replacing aging waterlines and modernize and fully connect the improving system capacity and water system infrastructure between reliability. Once the final project Awbrey Butte and Pilot Butte to wraps up, Bend will have a more improve system resilience. resilient and dependable water system better equiped to support With two of the four planned projects already complete, this the community for years to come. = Awbrey Butte Waterline - COMPLETE = Olney Avenue Waterline - COMPLETE = Second Street Waterline = Lafayette Waterline - FUTURE bendoregon.gov/2ndstreet-waterline”
Project location
NE Second Street from Olney Avenue to Lafayette Avenue
“NE Second Street from Olney Avenue to Lafayette Avenue”
Project location extension
Lafayette Avenue from NE Second Street to the western edge of NE Third Street
“Lafayette Avenue from NE Second Street to the western edge of NE Third Street”
Delivery phasing
Construction will be completed in three phases, with traffic control and temporary bypass routing used to maintain access and service.
“026 • Project Completion - End of 2026 *Dates are estimates and subject to change. What to Expect During Construction • Construction will be completed in three phases to help reduce disruptions • Single lane travel with traffic control to allow business access during construction • Brief water service disruptions to bypass water routing during construction, advance notice will be given prior to disruptions bendoregon.gov/2ndstreet-waterline”
Project code
1SWGR
“1SSFU - Support Facilities Upgrade 5 - 500,000 500,000 - - 1,000,000 1SSW3 - SW Sewer Basin Improvements Phase 3 5 1,325,000 5,100,000 1,700,000 - - 8,125,000 1SWGR - WRF Grit Removal 5 750,000 3,000,000 2,000,000 - - 5,750,000 1TABB - Archie Briggs Bridge Replacement 5 - 500,000 950,000 50,000 - 1,500,000 1TBMW - Butler Market & Wells Acres Improvements 2 2,100,000 - - - - 2,100,000 Total for Water Recl”
Capital program total
$5,750,000 USD
“1SSFU - Support Facilities Upgrade 5 - 500,000 500,000 - - 1,000,000 1SSW3 - SW Sewer Basin Improvements Phase 3 5 1,325,000 5,100,000 1,700,000 - - 8,125,000 1SWGR - WRF Grit Removal 5 750,000 3,000,000 2,000,000 - - 5,750,000 1TABB - Archie Briggs Bridge Replacement 5 - 500,000 950,000 50,000 - 1,500,000 1TBMW - Butler Market & Wells Acres Improvements 2 2,100,000 - - - - 2,100,000 Total for Water Recl”
Capital program schedule
FY2025-26: 750,000, FY2026-27: 3,000,000, FY2027-28: 2,000,000
“1SSFU - Support Facilities Upgrade 5 - 500,000 500,000 - - 1,000,000 1SSW3 - SW Sewer Basin Improvements Phase 3 5 1,325,000 5,100,000 1,700,000 - - 8,125,000 1SWGR - WRF Grit Removal 5 750,000 3,000,000 2,000,000 - - 5,750,000 1TABB - Archie Briggs Bridge Replacement 5 - 500,000 950,000 50,000 - 1,500,000 1TBMW - Butler Market & Wells Acres Improvements 2 2,100,000 - - - - 2,100,000 Total for Water Recl”
Funding source
City of Bend Water Reclamation Fund
“1SSFU - Support Facilities Upgrade 5 - 500,000 500,000 - - 1,000,000 1SSW3 - SW Sewer Basin Improvements Phase 3 5 1,325,000 5,100,000 1,700,000 - - 8,125,000 1SWGR - WRF Grit Removal 5 750,000 3,000,000 2,000,000 - - 5,750,000 1TABB - Archie Briggs Bridge Replacement 5 - 500,000 950,000 50,000 - 1,500,000 1TBMW - Butler Market & Wells Acres Improvements 2 2,100,000 - - - - 2,100,000 Total for Water Reclamation $ 24,095,000 $ 18,830,000 $ 17,570,000 $ 20,150,000 $ 18,500,000 $ 99,145,000”
Owner
City of Bend
“RESOLUTION NO. A RESOLUTION OF THE CITY COUNCIL ADOPTING THE 2026-2030 CAPITAL IMPROVEMENT PROGRAMS Findings: A. The City’s Fiscal Policies state that a five-year Capital Improvement Program (CIP) encompassing all City facilities shall be prepared and updated annually. B. The five-year CIP will be incorporated into the City’s budget and long-range financial planning processes. C. Changes to the CIP such as the addition of new projects, changes in scope and costs of a project or reprioritization of projects will require City Council or City Manager approval. Now, therefore, based on these findings, THE CITY COUNCIL OF THE CITY OF BEND RESOLVES AS FOLLOWS: 1. To adopt the 2026-2030 Capital Improvement Programs, as shown in Exhibit A. Adopted by the Bend City Council on June 18, 2025. YES: NO: ________________________________ Melanie Kebler, Mayor ATTEST: ____________________________ Ashley Bontje, City Recorder’s Office Approved as to form: __________________”
Governing action
Bend City Council adopted the 2026-2030 Capital Improvement Programs shown in Exhibit A.
“RESOLUTION NO. A RESOLUTION OF THE CITY COUNCIL ADOPTING THE 2026-2030 CAPITAL IMPROVEMENT PROGRAMS Findings: A. The City’s Fiscal Policies state that a five-year Capital Improvement Program (CIP) encompassing all City facilities shall be prepared and updated annually. B. The five-year CIP will be incorporated into the City’s budget and long-range financial planning processes. C. Changes to the CIP such as the addition of new projects, changes in scope and costs of a project or reprioritization of projects will require City Council or City Manager approval. Now, therefore, based on these findings, THE CITY COUNCIL OF THE CITY OF BEND RESOLVES AS FOLLOWS: 1. To adopt the 2026-2030 Capital Improvement Programs, as shown in Exhibit A. Adopted by the Bend City Council on June 18, 2025. YES: NO: ________________________________ Melanie Kebler, Mayor ATTEST: ____________________________ Ashley Bontje, City Recorder’s Office Approved as to form: __________________”