Willamette Water Supply Water Treatment Plant (WTP_1.0)

The WWSS Commission's new seismically resilient treatment plant in Sherwood is designed for an initial 60 million gallons per day and eventual 120 million gallons per day. Official publications connect design/permitting, historical subcontract procurement and reported construction progress. Sundt is the published CM/GC. The undated project page reports nearly 91 percent complete; commissioning, final acceptance and available remaining packages are unverified.

Last verified Oct 9, 2026 2 official source families

What is proposed

The WWSS Commission's new seismically resilient treatment plant in Sherwood is designed for an initial 60 million gallons per day and eventual 120 million gallons per day. Official publications connect design/permitting, historical subcontract procurement and reported construction progress. Sundt is the published CM/GC. The undated project page reports nearly 91 percent complete; commissioning, final acceptance and available remaining packages are unverified.

April 2021 fact sheet reports plant design and permitting underway

Revision U_04142021 describes the same Sherwood/Tonquin treatment plant, initial 60 mgd capacity and future 120 mgd design. This is the document's revision month, not the first public appearance or an approval date. Anticipated 2022 construction and 2026 operations remain historical forecasts.

Verify commissioning, final acceptance and any remaining purchasing packages

Timing is not established in reviewed records.

Confirmed work and commercial interpretation

What is proposed

The WWSS Commission's new seismically resilient treatment plant in Sherwood is designed for an initial 60 million gallons per day and eventual 120 million gallons per day. Official publications connect design/permitting, historical subcontract procurement and reported construction progress. Sundt is the published CM/GC. The undated project page reports nearly 91 percent complete; commissioning, final acceptance and available remaining packages are unverified.

Potential commercial work

Waterline IQ interpretation of accepted scope. These items are not confirmed contract packages or specifications.

Treatment plant

Water treatment plant and Water treatment filtration

Process and controls

Process piping and valves and Electrical and controls

Civil and site work

Seismic water infrastructure

Documented permitting

Permit records have not been captured; requirements and approval remain unverified.

Key official milestones

  1. Official event

    April 2021 fact sheet reports plant design and permitting underway

    Revision U_04142021 describes the same Sherwood/Tonquin treatment plant, initial 60 mgd capacity and future 120 mgd design. This is the document's revision month, not the first public appearance or an approval date. Anticipated 2022 construction and 2026 operations remain historical forecasts.

    View evidence for April 2021 fact sheet reports plant design and permitting underway
  2. Official forecast

    Historical GMP 1 forecast lists September–November 2021 subcontract bidding

    The official CM/GC procurement page anticipated September 27 advertisement and November 4, 2021 responses; GMP 2 separately lists August–September 2023. These elapsed advertised schedules do not establish an active solicitation, received bids, award amount or executed prime contract. SmartBid/confidential package access is outside the collected public evidence.

    View evidence for Historical GMP 1 forecast lists September–November 2021 subcontract bidding
Evidence and sources
4 accepted claims across 3 official document versions
Selected official evidence · Inspect exact excerpts and locators

WWSP: water treatment plant

WWSP sitemap-listed program and project publications
Inspect exact excerpt and locator
“Construction is nearly 91 percent complete on the WTP_1.0 Project. At the height of construction, about 300 workers that represent hundreds of local and regional businesses will provide the skills and expertise to complete the work. Dozens of other companie...”

Project Fact Sheet

WWSP official project-library document discovery
Inspect exact excerpt and locator
“Water Treatment Plant Tualatin Valley Water District (TVWD), the City of Hillsboro and the City of Beaverton are developing the Willamette Water Supply System. The new system will draw water from the mid-Willamette River at Wilsonville and, once treated, de...”

WWSP: wtpprocurement

WWSP sitemap-listed program and project publications
Inspect exact excerpt and locator
“GMP 1: Bid advertises Sept. 27, 2021. Bids due Nov. 4, 2021 @ 3 pm (PT). Scopes include erosion control, tree protection, tree removal, earthwork, underground yard piping, temporary electrical, long-lead equipment purchases, structural concrete, structural ...”