Construction solicitation advertised

Oct 24, 2024

The Contractor was selected through a competitive low-bid process. The bid documents were advertised on the City’s Bonfire platform on October 24, 2024. Three bids were received on November 26, 2024.

Exact wording from the City's document. The highlight is the supporting sentence.

Awbrey Glen and Westside Pump Station construction award issue summary — December 18, 2024

City of Bend · PDF page 2

Retrieved Jul 14, 2026

Open the City's PDF, page 2

This document also supports

Verification detailsPreserved copy, document fingerprint
Retrieved
Jul 14, 2026
Publisher
City of Bend
Source location
PDF page 2
Preserved copy
Version 1 kept by Waterline IQ
Document fingerprint (SHA-256)
83ca0e6f801980891e312ef82c68fc822326d1600d15ba69899264d89fe4a6ad
Excerpt · PDF page 2
e main cleaning), and the components to more easily bypass the force main in the case of emergency. The Contractor was selected through a competitive low-bid process. The bid documents were advertised on the City’s Bonfire platform on October 24, 2024. Three bids were received on November 26, 2024. The Engineer of Record’s (EOR) total project estimate based on the final design was $5,010,000. Emery & Sons Construction’s bid amount ($5,742,480) is 15% higher than the EOR’s estimate, but was the lowest bid received from a responsible and responsive bidder. While the contract price is slightly higher than the Engineer’s cost estimate, City staff recommends approval of this contract. Contract costs are consistent with the technical nature of the work and current limitations on material acquisition. The Notice to Proceed (NTP) is anticipated to be issued in January 2025 with construction beginning within 4 weeks of NTP. Initial improvements to the Westsid