Awbrey Glen and Westside Pump Station construction award issue summary — December 18, 2024

The Notice to Proceed (NTP) is anticipated to be issued in January 2025 with construction beginning within 4 weeks of NTP.

Exact wording from the City's document.

Awbrey Glen and Westside Pump Station construction award issue summary — December 18, 2024

City of Bend · PDF page 2

Retrieved Jul 14, 2026

Open the City's PDF, page 2
Verification detailsPreserved copy, document fingerprint
Retrieved
Jul 14, 2026
Publisher
City of Bend
Source location
PDF page 2
Preserved copy
Version 1 kept by Waterline IQ
Document fingerprint (SHA-256)
83ca0e6f801980891e312ef82c68fc822326d1600d15ba69899264d89fe4a6ad
Excerpt · PDF page 2
e consistent with the technical nature of the work and current limitations on material acquisition. The Notice to Proceed (NTP) is anticipated to be issued in January 2025 with construction beginning within 4 weeks of NTP. Initial improvements to the Westside Pump Station force main are anticipated to be in progress prior to commencement of the adjacent Olney Pedestrian and Bicy