Source
Awbrey Glen and Westside Pump Station construction award issue summary — December 18, 2024
Contract completion date for both pump station locations is August 2026.
Exact wording from the City's document.
Awbrey Glen and Westside Pump Station construction award issue summary — December 18, 2024
City of Bend · PDF page 3
Retrieved Jul 14, 2026
Verification detailsPreserved copy, document fingerprint
- Retrieved
- Jul 14, 2026
- Publisher
- City of Bend
- Source location
- PDF page 3
- Preserved copy
- Version 1 kept by Waterline IQ
- Document fingerprint (SHA-256)
83ca0e6f801980891e312ef82c68fc822326d1600d15ba69899264d89fe4a6ad
with the Olney construction contractor to reduce impacts to the public. Contract completion date for both pump station locations is August 2026. Budget and Financial Impacts: These expenditures are included in the CIP as 1SPS1 Awbrey Glen and Westside Pump Station Improvement Project as well as the Pum