Awbrey Glen and Westside Pump Station construction award issue summary — December 18, 2024

Contract completion date for both pump station locations is August 2026.

Exact wording from the City's document.

Awbrey Glen and Westside Pump Station construction award issue summary — December 18, 2024

City of Bend · PDF page 3

Retrieved Jul 14, 2026

Open the City's PDF, page 3
Verification detailsPreserved copy, document fingerprint
Retrieved
Jul 14, 2026
Publisher
City of Bend
Source location
PDF page 3
Preserved copy
Version 1 kept by Waterline IQ
Document fingerprint (SHA-256)
83ca0e6f801980891e312ef82c68fc822326d1600d15ba69899264d89fe4a6ad
Excerpt · PDF page 3
with the Olney construction contractor to reduce impacts to the public. Contract completion date for both pump station locations is August 2026. Budget and Financial Impacts: These expenditures are included in the CIP as 1SPS1 Awbrey Glen and Westside Pump Station Improvement Project as well as the Pum