Skip to main content
Waterline IQ — Water Infrastructure

Source for

Funding: awarded

Dec 18, 2024

The current DEQ loan amount is $5,310,000. The City is in the process of requesting additional loan funding to cover the total anticipated project costs. • City Manager amendment authority is requested to cover potential construction cost change orders in the amount of 10% of the original contract price.

Exact wording from the City's document. The highlight is the supporting sentence.

Awbrey Glen and Westside Pump Station construction award issue summary — December 18, 2024

City of Bend · PDF page 1

Retrieved Jul 14, 2026

Open the City's PDF, page 1

This document also supports

Verification detailsPreserved copy, document fingerprint
Retrieved
Jul 14, 2026
Publisher
City of Bend
Source location
PDF page 1
Preserved copy
Version 1 kept by Waterline IQ
Document fingerprint (SHA-256)
83ca0e6f801980891e312ef82c68fc822326d1600d15ba69899264d89fe4a6ad
Excerpt · PDF page 1
procurement process in accordance with the City’s Municipal Code Chapter 1.55, Public Contracts. • This project is funded via a loan from the Oregon Department of Environmental Quality (DEQ) under the Clean Water State Revolving Fund (CWSRF). The current DEQ loan amount is $5,310,000. The City is in the process of requesting additional loan funding to cover the total anticipated project costs. • City Manager amendment authority is requested to cover potential construction cost change orders in the amount of 10% of the original contract price. Add bu