Ashland Water Treatment Plant Resilience Project
The system is replacing the water treatment plant with a new 7.0 MGD direct filtration plant (with the ability to expand to 9.0 MGD for future demands). The WTP improvements include adding ozone, replacing the sand filter, chlorine feed, and flocculation basin. They will also add solar panels to offset the energy costs. The engineering design is done so this project is only for construction and construction management.
Last verified Sep 25, 2026 3 official source families
Project brief
What is proposed
The system is replacing the water treatment plant with a new 7.0 MGD direct filtration plant (with the ability to expand to 9.0 MGD for future demands). The WTP improvements include adding ozone, replacing the sand filter, chlorine feed, and flocculation basin. They will also add solar panels to offset the energy costs. The engineering design is done so this project is only for construction and construction management.
Latest material change
Owner’s representative awarded to West Yost
The City project update reports selection of West Yost as owner’s representative and negotiation of Phase I scope and fee.
Commercial scope
Confirmed work and commercial interpretation
What is proposed
The system is replacing the water treatment plant with a new 7.0 MGD direct filtration plant (with the ability to expand to 9.0 MGD for future demands). The WTP improvements include adding ozone, replacing the sand filter, chlorine feed, and flocculation basin. They will also add solar panels to offset the energy costs. The engineering design is done so this project is only for construction and construction management.
Potential commercial work
Waterline IQ interpretation of accepted scope. These items are not confirmed contract packages or specifications.
Treatment plant
Water treatment plant and Water treatment filtration
Pumping and storage
Process pumps
Process and controls
Electrical and controls
Civil and site work
Seismic water infrastructure
Selected lifecycle
Key official milestones
-
Official event
Added during OHA's 3Q2024 DWSRF priority-list cycle
OHA lists the project for DWSRF funding consideration; the workbook does not establish a formal procurement date.
View evidence for Added during OHA's 3Q2024 DWSRF priority-list cycle -
Official event
OHA publishes project in revised DWSRF public-comment list
The project appears in OHA's June 9, 2026 revised public-comment PPL, preserving a second official project-specific publication record.
View evidence for OHA publishes project in revised DWSRF public-comment list
Evidence and sources
10 accepted claims across 3 official document versions
Selected official evidence · Inspect exact excerpts and locators
Ashland Water Treatment Plant
Ashland water-treatment-plant project updates“Final engineering, permitting and bidding are anticipated to wrap up in Winter 2026, with construction beginning shortly thereafter. Once underway, construction is expected to span approximately three years as this critical infrastructure investment takes s...”
Ashland Water Treatment Plant
Ashland water-treatment-plant project updates“Awarded the Owners Rep to West Yost. Currently we are negotiating Scope & Fee for Phase I”
2026 Q3 Combined Base DWSRF and IIJA General Supplemental PPL
OHA DWSRF infrastructure project priority list“30 | City of Ashland SD-24-420 Jackson Marta Tarantsey / Tawni Bean 20,700 | | Issue: The existing water treatment plant was built in 1948 and has reached the end of its useful life and is located near Ashland Creek so it is prone to flooding and other nat...”
2026 Q3 Combined Base DWSRF and IIJA General Supplemental PPL — public-comment PDF
OHA DWSRF infrastructure project priority list — public-comment edition“rought resiliency and increase wildfire protection. City of Ashland Issue: The existing water treatment plant was built in 1948 and has Rating results include: SD-24-420 reached the end of its useful life and is located near Ashland Creek 5 pts (Health Risk...”