Location
Sandy, Oregon
Project code
SD-23-385

Sandy Water Treatment and Transmission Improvements

The project involves construction of 11,500 ft of 24” diameter transmission line to convey treated water from PWB’s filtration plant, new pump station, and reservoir repairs/replacements and improvements.

Last verified Sep 25, 2026 3 official source families

What is proposed

The project involves construction of 11,500 ft of 24” diameter transmission line to convey treated water from PWB’s filtration plant, new pump station, and reservoir repairs/replacements and improvements.

OHA publishes project in revised DWSRF public-comment list

The project appears in OHA's June 9, 2026 revised public-comment PPL, preserving a second official project-specific publication record.

Business Oregon financing invitation and confirmation of the current project delivery plan

Jul 2026–Jun 2027 Moderate confidence

Waterline IQ forecast

Confirmed work and commercial interpretation

What is proposed

The project involves construction of 11,500 ft of 24” diameter transmission line to convey treated water from PWB’s filtration plant, new pump station, and reservoir repairs/replacements and improvements.

Potential commercial work

Waterline IQ interpretation of accepted scope. These items are not confirmed contract packages or specifications.

Treatment plant

Water treatment plant and Water treatment filtration

Distribution

Transmission water main

Pumping and storage

Process pumps

Process and controls

Electrical and controls

Key official milestones

  1. Official event

    Added during OHA's 1Q2023 DWSRF priority-list cycle

    OHA lists the project for DWSRF funding consideration; the workbook does not establish a formal procurement date.

    View evidence for Added during OHA's 1Q2023 DWSRF priority-list cycle
  2. Official event

    Transmission-main construction bids due

    The City invitation to bid set April 15, 2025 as the bid deadline for the 16-inch transmission-main package.

    View evidence for Transmission-main construction bids due
  3. Official event

    Transmission-main construction contract authorized

    City Council authorized a construction contract with N8 Excavation for the transmission-main package in an amount not to exceed $2,687,000.

    View evidence for Transmission-main construction contract authorized
  4. Official event

    OHA publishes project in revised DWSRF public-comment list

    The project appears in OHA's June 9, 2026 revised public-comment PPL, preserving a second official project-specific publication record.

    View evidence for OHA publishes project in revised DWSRF public-comment list
Evidence and sources
11 accepted claims across 4 official document versions
Selected official evidence · Inspect exact excerpts and locators

Sandy City Council adopted minutes — May 19, 2025

Sandy water transmission procurement records
Inspect exact excerpt and locator
“MOTION: Authorize the City Manager to execute the construction contract with N8 Holmlund Inc, DBA N8 Excavation for the Transmission Main portion of the Portland to Sandy Water Filtration System project, in an amount not to exceed $2,687,000, as amended Mot...”

2026 Q3 Combined Base DWSRF and IIJA General Supplemental PPL

OHA DWSRF infrastructure project priority list
Inspect exact excerpt and locator
“8 | City of Sandy SD-23-385 Clackamas Jeff Hampton / Matt Mattia 11,180 | | Issue: With PWB’s new filtration plant, the current transmission line to purchase water only allows for raw water to be distributed. The option of building a new/updated treatment ...”

Portland to Sandy Water Filtration Transmission System invitation to bid

Sandy water transmission procurement records
Inspect exact excerpt and locator
“Sealed bids for the construction of Portland to Sandy Water Filtration Transmission System (Project) must be delivered to the City of Sandy (Owner), 39250 Pioneer Boulevard, Sandy, Oregon 97055, and addressed to AJ Thorne, Assistance Public Works Director, ...”

2026 Q3 Combined Base DWSRF and IIJA General Supplemental PPL — public-comment PDF

OHA DWSRF infrastructure project priority list — public-comment edition
Inspect exact excerpt and locator
“treatment facility, and intertie with Oak Lodge. City of Sandy Issue: With PWB’s new filtration plant, the current transmission line to Rating results include: SD-23-385 purchase water only allows for raw water to be distributed. The option 40 pts (Health R...”